Soil survey - excavation and compaction - costs

  • Erstellt am 2016-10-18 07:51:55

Flori2904

2016-10-18 07:51:55
  • #1
Hello,

we have had a soil survey prepared for a plot of land we want to acquire. A single-family house without a basement is to be built here.

We are now interested in the approximate additional costs for excavation, filling, compaction, and for the compaction certificate.

Excerpt from the soil survey:

"Building ground:
widespread up to 40 cm thick, humic, sandy,
artificial fillings; below are up to max. 1.9 m thick,
sandy, artificial fillings ([SU*]) in loose to
medium dense layering, containing brick remnants; below follows
up to max. 2.8 m below ground surface (BS 2/16) sand/gravelly sand (SU*) in
loose to medium dense layering; underlying is up to max.
4.3 m below ground surface (BS 1/16) sand/gravelly clay (SU*) in
medium dense layering; down to the final depth of 6.0 m below ground surface
(BS 1/16) fine sands (SU*, SU) in medium dense to dense
layering were encountered

Conclusion:
replacement of the humic, root-penetrated soils/fillings with
at least 1.5 m thickness
Foundation: shallow foundation; assumption top finished floor ground floor = 0.3 m BP (preliminary planning),
i.e. approx. 50 cm above the level of the BS 1/16 sounding

Base slab:
bearing reinforced base slab (footing slab) with frost skirts;
bedding modulus (ks) = 12 MN/m³
bedding cushion of sand/gravel below the base slab
allowable pressures beneath the footing slab: approximately 100 kN/m²
strip foundations (frost skirts): embedment depth = 0.80 m
foundation width 0.3 m
allowable base stress = 150 kN/m2
(design value R/d = 210 kN/m2)

Frost zone:
Zone II, area 4, maximum frost penetration depth 105 cm (RSto 2001)

Water level:
groundwater encountered from 5.31 m below ground surface in BS 1/16

Water management:
not required, dry holding of the construction site
Building waterproofing for non-basement construction:
Waterproofing according to DIN 18195-4 against soil moisture,
WU guideline: stress class 2

Infiltration:
sustainable infiltration on site into the fillings and
silty sands not possible or not recommended

Note on earthworks:
Earth leveling must be compacted again; application of at least 30 cm thick
gravel layer at footing level, then installation of soil replacement and
a terrain fill of non-cohesive soils (GW, SW) with max. approx. 2.4 m is
to be planned – verification of at least medium dense layering of the
gravel layer, soil replacement and terrain fill;
control test (compaction certificate) under external supervision is recommended
 

Flori2904

2016-10-18 08:43:04
  • #2
What I forgot, the dimensions of the Scanhaus Marlow Marlow:

It is a Scanhaus Marlow Marlow 122 sqm,
9.88 x 7.78 m.
 

stefanc84

2017-02-19 02:54:01
  • #3
What was the end result? 2.4m soil replacement sounds intense.
 

Similar topics
18.09.2012Construction of a base slab with frost skirt but without foundation10
09.09.2013Costs for soil replacement, soil survey for construction ground, clayey25
24.07.2014Soil assessment report, filling - additional costs?11
11.11.2015Home financing with a low salary?!28
10.08.2016Soil report - silty and artificial fill11
20.08.2016Base slab vs strip foundation15
27.03.2017Backfilling for foundation slab25
01.06.2019Bending-resistant base plate driven over by truck in less than 1 day23
02.10.2019Base plate - film against rising moisture15
13.10.2020Load-bearing foundation structure, foundation cushion for floor slab27
10.07.2020Assessment of Soil Report - Experiences14
13.01.2025Insulating wooden floor panel with straw20
14.08.2020Potato cellar - floor slab - construction25
20.12.2022Lowering of groundwater according to soil report - Your experiences?57
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
31.07.2023Is a soil survey necessary when a geotechnical report is available?17
14.08.2023Does the builder have to hand over the soil report?18
03.03.2024Basement or ground slab: which is more sensible for the property situation?55
01.11.2024Danwood complete offer vs. separate commissioning architect13

Oben