Screed - incorrect height - how to fix?

  • Erstellt am 2022-08-30 10:14:46

Dali2020

2022-08-31 12:03:06
  • #1


No, he's actually quite nice.
We will just wait and see what the site manager or his representative says about it. We simply want it to fit afterwards and for there to be no technical or visual defects. How that is achieved is secondary for us at first.
 

Dali2020

2022-08-31 12:04:20
  • #2


I don't understand the question.
First the tiles are laid, then the parquet is glued down, and afterwards the expansion joints are filled.
 

Neubau2022

2022-08-31 12:17:34
  • #3


Ok. Got it. Our tiler works with rails where the rubber part is replaceable.
 

Dali2020

2022-08-31 12:47:14
  • #4
To wrap things up:

We have spoken with the representative of the construction manager: No problem at all, it will be sanded down.

Thank you anyway for the numerous feedback.
 

ypg

2022-08-31 14:45:24
  • #5
Dowels are used. But it only works if the heating circuits behave similarly, meaning the expansion of the floor is the same.
 

motorradsilke

2022-08-31 14:58:40
  • #6
A silicone joint is simply placed exactly over the expansion joint. Right where the rail is in your case.
 