Screed drying apparently extremely slow

  • Erstellt am 2017-09-14 11:18:59

DragonyxXL

2017-09-14 11:18:59
  • #1
We received our cement screed on June 6th/7th. The screed then rested for 3 weeks with (1-3 times ventilation per day). This was followed by the 3-week heating program with correspondingly varying temperatures. Afterwards, another week was heated at a moderate temperature. By mid-August, the living room (intensive sunlight from 7 a.m. to 2 p.m.) was ready for covering. The other rooms (bedroom, children's room, etc., all with less sunlight) were still too damp. So, another 2 weeks of intensive heating and ventilation 3-4 times a day were done. The weather was of course not particularly helpful (very humid and still fairly warm at 20-26°C most of the time).

In the meantime, the screed has been in place for over 3 months or 14 weeks and the flooring installer measured values between 2.0 and 2.4 CM for the rooms. According to my understanding, we want to achieve <1.8 CM. Actually, values below 2.0 were measured already 2 weeks ago and today the values were above that again.

We moved in last weekend and would of course like to finish and use the rooms.

What can we do to achieve readiness for covering?
 

andimann

2017-09-15 09:20:20
  • #2
Hi,
why haven't you set up any [Bautrockner]? You can hardly get the moisture out of the house just by airing, especially in summer.

Rent / buy 2-3 [Bautrockner] and get started.

Best regards,

Andreas
 

DragonyxXL

2017-09-15 10:52:34
  • #3

No one had recommended that so far and until now we assumed it would no longer be necessary (until the moisture values stagnated/increased again). My initial research showed €40/rental day per unit. That means ~€550 for 2 units for one week. That’s really steep.

But those things do manage pretty significant amounts, right?
 

tomtom79

2017-09-15 11:08:57
  • #4
We once had a similar case here where the tiler just wanted to waste time, probably too much work.

Ps. add a lot of power for the [Bautrockner].
 

KlaRa

2017-09-16 18:43:56
  • #5
Hello questioner. Basically, I do not trust any CM measurement that I have not conducted myself. A standard cement screed without additives will reach readiness for laying at a thickness of 45mm and under the current (outdoor) climate conditions within about 6 weeks, provided that good and regular ventilation was carried out in the meantime. However, in screeds where additives have been used, it is quite possible that readiness for laying can be considered dry even with a CM residual moisture value above 2.0%. The definitive answer to this can be given by the screed installer who installed the screed and possibly used an additive. Please stay away from drying devices with a young screed! The disadvantages frequently arising from these can be considerable. It is better to set up several fans for proper air circulation and leave the windows of the rooms slightly open in the meantime. You can check yourself whether the screed actually still contains too much residual moisture. In two rooms, stick the edges of a thicker PE film measuring 50cm x 50cm each onto the screed with textile adhesive tape. Place an ordinary hygrometer, which deserves this name, under the foil beforehand. Now open the windows for ventilation and check after about 24 hours whether condensation has formed under the foil. Then the residual moisture would still be too high. If no condensation forms, look at the scale of the hygrometer. If the value is clearly below 70%, then the screed is very likely sufficiently dry for the installation of textile coverings. For elastic coverings and parquet, the value should not be higher than 65%. Critics may now raise their voices loudly, but with this method one can really obtain a very good estimate! --------------------- Regards: KlaRa
 

DragonyxXL

2017-09-21 09:33:17
  • #6
Until when is a screed considered "young"? It has now been 15 weeks since installation. Today the floor layer is back and measured 1.8-1.9. The installation will now take place.
 

Similar topics
02.01.2014Building dryer - a must?49
26.06.2015Floor plan question, stairs, window, orientation12
24.09.2015Which windows and doors are recommended?21
10.11.2015Single-family house floor plan planned, we like the windows43
21.02.2016Secure windows/front door for edge location34
22.01.2016Kitchen planning with island and floor-to-ceiling windows12
11.02.2016Windows / Doors / Wardrobe13
13.03.2016Change roof tile color to anthracite windows16
31.07.2016Electrical inspection, Q2, bathroom tiles, knee wall, floor-to-ceiling windows23
06.06.2016How much light does a window let in?17
14.11.2016Soundproofing - weakest link? (Windows?)26
03.12.2019Additional costs due to incorrectly planned ventilation system + floor-to-ceiling windows?50
23.12.2016Floor-to-ceiling windows - how to place the sofa?12
02.02.2017Is ventilation/drying after installing screed/interior plaster sensible?15
06.12.2017Is it sensible to use a dehumidifier after taking over the building or just ventilate by opening the windows?17
09.04.2020Visit the construction site for ventilation?17
17.02.2021Aluminum-wood triple-glazed window with internal condensation despite the warm edge16
12.09.2022Damp wall due to lack of ventilation after screed39
28.11.2023Install click vinyl despite possibly too high residual moisture.32

Oben