for my planned new construction (solid house 175 m² living space including basement) I request critical feedback on the payment schedule of my general contractor:
House with basement
2.5% upon submission of the building application
2.5% upon completion of the work planning and statics
5.0% upon completion of the foundation slab
15.0% upon completion of the basement ceiling
15.0% upon completion of the ground floor ceiling
19.0% upon completion of the carpentry work
19.0% upon completion of the interior plaster (except secondary plaster and filling work)
8.0% upon completion of the screed work
8.5% upon installation of the interior doors
4.0% upon completion of the exterior plaster
1.5% after full completion
Thank you in advance.
for my planned new construction (solid house 175 m² living space including basement) I request critical feedback on the payment schedule of my general contractor:
House with basement
2.5% upon submission of the building application
2.5% upon completion of the work planning and statics
5.0% upon completion of the foundation slab
15.0% upon completion of the basement ceiling
15.0% upon completion of the ground floor ceiling
19.0% upon completion of the carpentry work
19.0% upon completion of the interior plaster (except secondary plaster and filling work)
8.0% upon completion of the screed work
8.5% upon installation of the interior doors
4.0% upon completion of the exterior plaster
1.5% after full completion