Review Payment Schedule General Contractor Single-family House

  • Erstellt am 2014-11-18 20:12:10

Patchwork

2014-11-18 20:12:10
  • #1
Hello forum members,

for my planned new construction (solid house 175 m² living space including basement) I request critical feedback on the payment schedule of my general contractor:

House with basement

2.5% upon submission of the building application

2.5% upon completion of the work planning and statics

5.0% upon completion of the foundation slab

15.0% upon completion of the basement ceiling

15.0% upon completion of the ground floor ceiling

19.0% upon completion of the carpentry work

19.0% upon completion of the interior plaster (except secondary plaster and filling work)

8.0% upon completion of the screed work

8.5% upon installation of the interior doors

4.0% upon completion of the exterior plaster

1.5% after full completion

Thank you in advance.
 

Patchwork

2014-11-19 12:31:08
  • #2
@ construction expert. Thank you for the quick response. "after complete completion" means after acceptance with me and the site manager. External expert checks randomly (content of the construction/performance description). I am thinking about whether to commission one separately.
 

Similar topics
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
08.08.2016Payment before or after completion of the construction phase?51
28.02.2017Are securities customary for completion and warranty?24
19.08.2018Strategically well-planned handover completion under building supervision11
29.09.2020Building permit before completion of development31
14.11.2021Sell an apartment from a two-family house immediately after completion34
01.07.2022Construction delay without completion. The house simply is not finished21

Oben