Questions about the building permit

  • Erstellt am 2015-03-18 15:56:09

Bauexperte

2015-03-18 17:28:28
  • #1

Sure!

Rhenish greetings
 

Sebastian79

2015-03-18 17:30:34
  • #2
Why? You write "kein Notarvertrag" - that can only exist once you want to buy the item. A preliminary contract is common, but in what way binding?
 

Bauexperte

2015-03-18 17:41:07
  • #3

By signing at the notary?

In the fine print, you will find all sorts of exclusions explaining why the house cannot be handed over on 31.12.15 after all.

Just do the math yourself; it shouldn’t be too hard even as a layman :rolleyes: It’s March ... the notary appointment still has to be scheduled and is available for review for 14 days ... only then (and if all buyers of this parcel have signed) will the demolition be initiated; of course, all demolition contractors are waiting for this one order ... assuming in good faith that the building permit will be granted in the simplified approval process and everything, really everything runs smoothly, the building permit will be available at the earliest in June 15; the demolition is completed. Then the soil report must be prepared, the structural analysis commissioned, and the working plans created; this also takes 4 weeks if it goes quickly and we are in July. But that doesn’t mean the construction company can start immediately; it needs some preparation too; let’s say it’s fast, we are in August.

Now tell me—which house can be built and ready to move into within 4 months? Not taking company holidays into account in the remaining 4 months ….

Rhenish greetings
 

Sebastian79

2015-03-18 17:45:23
  • #4
ok, won :D
 

hanru2003

2015-03-18 20:49:34
  • #5
Hmm, I'll wait and see how this will go. I haven't signed anything. When the notary appointment comes, can't it only take place if he also has the building permit? Or does it also happen before without the building permit? The banks only give the green light once the building permit has been issued anyway, and I won't sign anything before the financing is finalized...
 

Sebastian79

2015-03-18 20:51:10
  • #6
A building permit is not a requirement for an approval of financing.
 

Similar topics
31.10.2008Is a building permit also required for a carport and equipment shed?13
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
22.10.2014When to finalize the financing??15
30.06.2015Question about financing (when changing the general contractor)16
28.11.2024Neighbor's lawsuit against approved building permit46
23.10.2015Quick Check Financing - Purchase from Private11
18.03.2016Influence of the neighbor in building permit18
16.01.2017No building permit as long as the land is not developed?10
26.02.2017Financing approved by the bank. Better house on offer.28
20.08.2017Issuance of the building permit?24
31.12.2017Winter garden conversion - building permit required or permit-free?15
08.01.2018According to the law, the building permit is automatically granted if12
22.01.2018Building on still foreign land - Waiting for building permit25
21.06.2018What must be included in the building permit? Legal certainty?19
29.08.2018Filling up a raised plot of land to make it level - building permit required?16
24.10.2018Broker sells house without current building permit. Notary costs?25
10.01.2020Construction loan without building permit possible?17
13.03.2021Construction start September 2021 - When to take care of financing?21
25.12.2021Planning phase: Building permit / Financing - Procedure14

Oben