Bauhamster1
2018-10-11 13:41:28
- #1
Hello everyone,
I would be very happy to receive answers to my questions and thank you in advance.
Current situation: Land available (building land with development plan)
Target situation: Development of the land with a single-family house including a basement with DEKRA construction supervision (acceptance of the individual trades)
Attached are the rough steps of building a house as I imagine it. Please feel free to add and/or correct the order.
1. Preliminary discussion with the preferred prefabricated house company
2. Building substance check and review of experience reports about the prefabricated house company
3. Verification of the prefabricated house company (financial situation)
4. Preliminary sampling of the offered equipment package for the fittings & factory tour of the production
5. Decision about the prefabricated house company made
6. Architect planning including soil testing and structural analysis
7. Creation of building plans, energy demand calculation, cross-section planning, living space calculation
8. Submission of building plans to the municipality (estimated up to 3 months until approval)
9. Loan application must be submitted and approved
10. After approval of the plan and the loan application (9 months interest-free provision period) signature at the prefabricated house company (contract of course checked for scope and completeness of trades)
11. Start of production by the prefabricated house company
12. Excavation, groundwork, and laying of supply & wastewater, internet, gas lines
13. Basement construction begins, finished basement including insulation
14. Basement construction completed
15. After completion of the house production delivery and assembly on basement slab
16. Shell construction stands
17. Roof truss stands
18. Interior work starts (electricity, insulation, plastering, etc.)
19. House finished, final acceptance
20. Move-in and completion of driveway, garden, etc.
Question:
Regarding point 2: Is some kind of preliminary contract with the prefabricated house company necessary here? The architect will hardly perform his work without financial security.
Regarding point 14: Is it disadvantageous if the basement is completed and the house assembly takes place a week later?
- By when do I need to have the bank financing at the latest? The 9 months from point 7 seem very tight to me! (Production of the house walls, etc. already takes several months)
- Is it correct that payments to the prefabricated house company are only made after "approval or acceptance" by the DEKRA building expert I commissioned?
I would be very happy to receive answers to my questions and thank you in advance.
Current situation: Land available (building land with development plan)
Target situation: Development of the land with a single-family house including a basement with DEKRA construction supervision (acceptance of the individual trades)
Attached are the rough steps of building a house as I imagine it. Please feel free to add and/or correct the order.
1. Preliminary discussion with the preferred prefabricated house company
2. Building substance check and review of experience reports about the prefabricated house company
3. Verification of the prefabricated house company (financial situation)
4. Preliminary sampling of the offered equipment package for the fittings & factory tour of the production
5. Decision about the prefabricated house company made
6. Architect planning including soil testing and structural analysis
7. Creation of building plans, energy demand calculation, cross-section planning, living space calculation
8. Submission of building plans to the municipality (estimated up to 3 months until approval)
9. Loan application must be submitted and approved
10. After approval of the plan and the loan application (9 months interest-free provision period) signature at the prefabricated house company (contract of course checked for scope and completeness of trades)
11. Start of production by the prefabricated house company
12. Excavation, groundwork, and laying of supply & wastewater, internet, gas lines
13. Basement construction begins, finished basement including insulation
14. Basement construction completed
15. After completion of the house production delivery and assembly on basement slab
16. Shell construction stands
17. Roof truss stands
18. Interior work starts (electricity, insulation, plastering, etc.)
19. House finished, final acceptance
20. Move-in and completion of driveway, garden, etc.
Question:
Regarding point 2: Is some kind of preliminary contract with the prefabricated house company necessary here? The architect will hardly perform his work without financial security.
Regarding point 14: Is it disadvantageous if the basement is completed and the house assembly takes place a week later?
- By when do I need to have the bank financing at the latest? The 9 months from point 7 seem very tight to me! (Production of the house walls, etc. already takes several months)
- Is it correct that payments to the prefabricated house company are only made after "approval or acceptance" by the DEKRA building expert I commissioned?