Hello everyone,

our house construction project is now about to start.

We had considered it at the end of 2022 but then decided against it due to all the uncertainties.

I am a bit unsure about the process, whether I might have forgotten something formal and important and am basically setting myself up for failure.

Land plot available - 1300 sqm in family ownership - according to the notary's division, my partner already owns the back half. Entry in the land register for 1/2 has been made.
The division must still be carried out by the surveyor in connection with the building application.
Division and building application proceed in parallel in Berlin. Development of the second row has been clarified - personally clarified with urban planning. The size will be adhered to.
Bank financing was approved today.

Now the question: Sign the construction contract now (offer suits us) and then it should be able to start.

Do you have any thought that I should definitely consider beforehand?

Thank you very much
 

11ant

2024-08-20 16:32:59
  • #2
Oh yes, you should consider that the house also needs to be designed, and that a freelance architect is better suited for this than an inclusive planner from a general contractor. A general contractor whose construction contract you agree to is only "half the rent," and in I have not read anything about planning or found anything else in your thread history. By the way, I seem to remember from that he would not build again with a general contractor.
 

Buddy0505

2024-08-20 18:30:21
  • #3
Thank you very much - in the meantime, 4 acquaintances have built with this company and are quite happy.
A bit of luck probably belongs to it ... do you think it makes sense to obtain information in advance from Creditreform? See HELMA insolvency
 

nordanney

2024-08-20 18:53:25
  • #4

You can obtain it. But with a construction company it is a) difficult for laypeople to derive anything from the figures and b) even for professionals not much can be deduced due to the business model with inventories/construction and later sales/payment receipts/activation possibilities.
A proper annual report with management report would be much more interesting – for example, with Helma you could read how badly it was going (on the earnings side).
 

Gerddieter

2024-08-20 20:49:52
  • #5
Is there a planned house with all details so that "the offer suits you"? Otherwise, please do not sign anything with the GU.
 

11ant

2024-08-20 21:38:53
  • #6

This probably raises the justified suspicion that the company does proper work. However, I was talking about design competence, which cannot be deduced from clean work. Planning is the architect's responsibility; general contractors usually take the "necessary" architectural services very literally.

Almost only the Easter Bunny believes that credit agencies can and would read balance sheets. It is far more useful for YOU to pay attention to the aspects of "completion guarantee" and "final payment." An insolvency can be just as irrelevant to you as you would have little to do with the administrator.
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
03.08.2012Contract Supplement to the Construction Contract by the Developer36
29.10.2013Property reserved, construction financing plan, architect/building permit application21
28.02.2015Building application submitted/open detailed questions/looking forward to suggestions39
15.06.2015Garage - Building Application - Confusion36
27.04.2017Carport deviation from the building application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?44
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
08.08.2018Neighbor objects after approved building application69
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
26.02.2019Submit a building application before the land is paid for?11
10.04.2019House purchase and division with multiple parties13
30.01.2021The building authority rejects the building application because the house is planned too far back86
15.07.2021Division of a semi-detached house along the roof ridge18
06.11.2022Fixed price offer with construction price index adjustment in the construction contract22