Eierpiepe
2021-05-26 10:00:46
- #1
Hello everyone,
We have agreed on a turnkey house contract with a fixed price for a single-family house with the general contractor. The contract was concluded in February 2021 and the basement is already in place. Now I received a letter stating that the prices for the roof construction and facade insulation are to be increased and the surcharge will be passed on to us 1:1.
I have studied the contract carefully and a labor/material price clause was definitely not agreed upon. (This was also marked accordingly in the contract).
Although I am just an amateur, in this case the contractor may not pass on a price increase to me, right? Of course, I can understand the contractor, but I did not agree on a fixed price for nothing in order to have planning security. In this case, I would say that is his problem?
Above all, the contract was only concluded in February 2021; the contractor could have negotiated a buffer or a clause due to the current sensitive situation.
On the other hand, of course I do not want to delay the progress of the construction.
How should I behave now?
Best regards
We have agreed on a turnkey house contract with a fixed price for a single-family house with the general contractor. The contract was concluded in February 2021 and the basement is already in place. Now I received a letter stating that the prices for the roof construction and facade insulation are to be increased and the surcharge will be passed on to us 1:1.
I have studied the contract carefully and a labor/material price clause was definitely not agreed upon. (This was also marked accordingly in the contract).
Although I am just an amateur, in this case the contractor may not pass on a price increase to me, right? Of course, I can understand the contractor, but I did not agree on a fixed price for nothing in order to have planning security. In this case, I would say that is his problem?
Above all, the contract was only concluded in February 2021; the contractor could have negotiated a buffer or a clause due to the current sensitive situation.
On the other hand, of course I do not want to delay the progress of the construction.
How should I behave now?
Best regards