berndn
2016-06-12 11:43:57
- #1
Hello dear house building forum!
I have been a silent reader of the house building forum for some time now. After a long search, we finally found a plot of land in the middle of last year, and now the planning is slowly starting.
It was clear early on that we wanted to build a solid house. At first, we had various appointments with architects and general contractors who created different sketches and designs for us.
In particular, the cooperation with the general contractors seemed very inflexible to us. Our wishes were only partially considered, and there were always the standard designs that can be found on the web.
Therefore, we decided to implement our project with an architect. In a second round, in which we spoke with various architects, we have now decided on an architect and signed an architect contract for phases 1-8.
Previous process:
We created a requirements profile with a room program that was handed over to the architect. Then there was an appointment at the architect’s office where we discussed our requirements. After an on-site appointment at the construction site, the surveyor was commissioned to measure the plot.
Now the architect began creating the first draft, which was presented to us last Thursday in the form of a floor plan and side views. There was also a floor area calculation and a cost estimate that includes the following points:
x m3 x 340 €/net = xxx € /net
xxx €/VAT
xxx €/gross
Overall cost breakdown:
Building with double garage xxx €/gross
Architect xxx €/gross
Surveyor xxx €/gross
Structural engineer xxx €/gross
Total costs xxx €/gross
This draft contains some details that we like very much but also a few points that deviate from our original requirements profile.
Example: double garage 6x8m instead of 4x8 + carport
Utility room on the ground floor instead of, as desired, on the upper floor
Open gallery above dining area, gallery was not desired by us. We are also not sure if we want that.
We made it clear to the architect that we still need to review the details and discuss them internally, especially regarding the gallery. The architect also told us that he would send us an interim invoice for the current status of services, which was also okay with us.
On Saturday we then received the interim payment with the following content:
Dear building owners,
according to the scope of services and attachment, we allow ourselves to issue a first interim invoice for xxx €/gross.
The following service phases are billed:
1. Basic evaluation 2% (of 2%)
2. Preliminary planning 7% (of 7%)
3. Design planning 7% (of 15%)
This surprised us because we actually still see ourselves in service phase 2. We did receive a first draft, but neither a rough schedule nor a cost estimate according to DIN 276, as provided in HOAI and the contract. Or is the above list sufficient for a cost estimate?
We contacted the architect on the same day to clarify the uncertainties. He told us that, of course, we would receive further drafts. He clearly considers us to already be in phase 3 (design planning).
Actually, we wanted to accept the interim payment so as not to cause any bad feelings right from the start. But we are still hesitating because we find the approach unusual and are not sure what consequences might arise if we accept the interim payment as is.
This results in the following questions for us:
- Is the cost estimate sufficient or should there not be at least a breakdown by cost groups (level 1)?
- What planning status must the preliminary planning have in order to start phase 3?
- Do you also see us already in phase 3? Or are our expectations possibly too high?
- Should a written acceptance of the result take place after each phase? How does that work for others?
We hope to receive some first answers to our questions here. What we are definitely already agreed on is that we will look for an expert as an independent instance as soon as possible.
Regards and many thanks in advance.
Bernd
I have been a silent reader of the house building forum for some time now. After a long search, we finally found a plot of land in the middle of last year, and now the planning is slowly starting.
It was clear early on that we wanted to build a solid house. At first, we had various appointments with architects and general contractors who created different sketches and designs for us.
In particular, the cooperation with the general contractors seemed very inflexible to us. Our wishes were only partially considered, and there were always the standard designs that can be found on the web.
Therefore, we decided to implement our project with an architect. In a second round, in which we spoke with various architects, we have now decided on an architect and signed an architect contract for phases 1-8.
Previous process:
We created a requirements profile with a room program that was handed over to the architect. Then there was an appointment at the architect’s office where we discussed our requirements. After an on-site appointment at the construction site, the surveyor was commissioned to measure the plot.
Now the architect began creating the first draft, which was presented to us last Thursday in the form of a floor plan and side views. There was also a floor area calculation and a cost estimate that includes the following points:
x m3 x 340 €/net = xxx € /net
xxx €/VAT
xxx €/gross
Overall cost breakdown:
Building with double garage xxx €/gross
Architect xxx €/gross
Surveyor xxx €/gross
Structural engineer xxx €/gross
Total costs xxx €/gross
This draft contains some details that we like very much but also a few points that deviate from our original requirements profile.
Example: double garage 6x8m instead of 4x8 + carport
Utility room on the ground floor instead of, as desired, on the upper floor
Open gallery above dining area, gallery was not desired by us. We are also not sure if we want that.
We made it clear to the architect that we still need to review the details and discuss them internally, especially regarding the gallery. The architect also told us that he would send us an interim invoice for the current status of services, which was also okay with us.
On Saturday we then received the interim payment with the following content:
Dear building owners,
according to the scope of services and attachment, we allow ourselves to issue a first interim invoice for xxx €/gross.
The following service phases are billed:
1. Basic evaluation 2% (of 2%)
2. Preliminary planning 7% (of 7%)
3. Design planning 7% (of 15%)
This surprised us because we actually still see ourselves in service phase 2. We did receive a first draft, but neither a rough schedule nor a cost estimate according to DIN 276, as provided in HOAI and the contract. Or is the above list sufficient for a cost estimate?
We contacted the architect on the same day to clarify the uncertainties. He told us that, of course, we would receive further drafts. He clearly considers us to already be in phase 3 (design planning).
Actually, we wanted to accept the interim payment so as not to cause any bad feelings right from the start. But we are still hesitating because we find the approach unusual and are not sure what consequences might arise if we accept the interim payment as is.
This results in the following questions for us:
- Is the cost estimate sufficient or should there not be at least a breakdown by cost groups (level 1)?
- What planning status must the preliminary planning have in order to start phase 3?
- Do you also see us already in phase 3? Or are our expectations possibly too high?
- Should a written acceptance of the result take place after each phase? How does that work for others?
We hope to receive some first answers to our questions here. What we are definitely already agreed on is that we will look for an expert as an independent instance as soon as possible.
Regards and many thanks in advance.
Bernd