Payment plan, tips and notes

  • Erstellt am 2013-05-17 22:32:13

Vit84

2013-05-17 22:32:13
  • #1
Hello community,

I currently have an offer with the following payment plan:

1) Submission of building application 10.0 %
less 5% security retention for the timely completion
of the work without significant defects (§ 632a Building Code)
2) Completion of foundation slab 15.0 %
3) Completion of ground floor ceiling 15.0 %
4) Completion of shell construction including roof truss 10.0 %
5) Completion of roofing works 7.0 %
6) Completion of window installation without window sills 7.5 %
7) Completion of exterior plaster, first layer 5.0 %
8) Completion of rough installation of sanitary and electrical work 12.0 %
9) Completion of interior plaster, underfloor heating and screed 13.0 %
10) Completion of interior doors 3.0 %
11) Completion of exterior plaster, second layer 2.5 %
12) Acceptance and handover to the client, payout of retention from 1)
Rate for deep drilling Total: ………………………………………….. will be invoiced after the service has been provided and offset against the 8th rate according to the payment plan.
Additional costs become due for payment when the execution has been carried out.

I would be interested to know what you think about this. I would be grateful for any tips and advice.
 

Bauexperte

2013-05-18 10:30:27
  • #2
Hello,


Real retention or guaranteed by bank guarantee?


Apart from the fact that the text block still needs to be changed – deep drilling – I would only release the retention when the construction project is ready for handover without major defects; that is, after installment 11 and not before.

Overall, I cannot find any flaws in the payment schedule, and the weighting of the individual payment steps is fair for both sides.

Regards from the Rhineland
 

Vit84

2013-05-20 21:29:27
  • #3
Ok, thanks to [Bauexperte].... what about the other experts?? No one has an opinion on this???? I would be happy....
 

Similar topics
26.09.2013What do you think of this payment plan?, Property appraisal18
08.12.2015Payment plan: paid too much at the beginning?11
16.02.2016Question about contractual completion14
26.02.2016Renegotiation of payment plan, please help25
03.09.2016Buy the kitchen more than a year before completion?54
01.08.2017Questions about the payment plan10
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
28.02.2017Are securities customary for completion and warranty?24
22.03.2017Is a high first installment common in a payment plan?23
17.07.2017Payment plan okay - 13% after the floor slab?21
18.08.2017First invoice for earthworks and base slab due25
30.06.2018Construction contract - Uncertainty regarding payment schedule33
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
19.08.2018Strategically well-planned handover completion under building supervision11
30.09.2018Payment Plan for Prefabricated House - Reviews and Experiences Desired10
29.11.2020Accept payment plan despite legal defects?12
07.05.2019Payment plan - unreliable? Your assessment11
11.12.2020Payment plan and unpleasant feeling11
29.02.2024Payment plan - 5% retention not regulated11
11.07.2024Payment plan for shell construction - market-oriented?17

Oben