Grottenolm
2013-11-24 18:44:02
- #1
Hello everyone,
we are about to sign a construction contract - we provide the land ourselves, the construction company will do the earthworks and shell construction themselves and subcontract the rest to local companies.
The draft contract includes the following payment schedule, which seems very unbalanced to me as a layperson:
What is your impression? How could this payment schedule be improved? (I don’t just want to say "it doesn’t fit," but I have to specify exactly how it should be from my point of view.)
Thank you in advance!
Olm
we are about to sign a construction contract - we provide the land ourselves, the construction company will do the earthworks and shell construction themselves and subcontract the rest to local companies.
The draft contract includes the following payment schedule, which seems very unbalanced to me as a layperson:
[*]after building application (we are building with building notification!): 5%
[*]after base slab: 15%
[*]after ground floor ceiling: 20%
[*]after framing the roof structure: 15%
[*]after roof covering: 10%
[*]after window installation: 8%
[*]after interior plastering: 8%
[*]after screed: 7%
[*]after start of tiling works: 7%
[*]after handover of the construction work: 5%
What is your impression? How could this payment schedule be improved? (I don’t just want to say "it doesn’t fit," but I have to specify exactly how it should be from my point of view.)
Thank you in advance!
Olm