RayB
2024-07-08 23:11:45
- #1
Hello,
as our construction project is entering the final decision phase, I wanted to ask whether the payment schedule submitted by the shell builder complies with market requirements or should be renegotiated.
The following payment schedule was presented to us:
10% Contract signing
15% Completion of basement floor slab
20% Completion of basement ceiling
30% Completion of ground floor ceiling +L-Stones (Tiefhof) and sewer pipes
20% Completion of upper floor ceiling
5% Final invoice
I wonder if 45% of the total amount just for the basement is not considered too high? What are the opinions on this?
as our construction project is entering the final decision phase, I wanted to ask whether the payment schedule submitted by the shell builder complies with market requirements or should be renegotiated.
The following payment schedule was presented to us:
10% Contract signing
15% Completion of basement floor slab
20% Completion of basement ceiling
30% Completion of ground floor ceiling +L-Stones (Tiefhof) and sewer pipes
20% Completion of upper floor ceiling
5% Final invoice
I wonder if 45% of the total amount just for the basement is not considered too high? What are the opinions on this?