Payment Plan for Prefabricated House - Reviews and Experiences Desired

  • Erstellt am 2018-09-28 20:27:11

Fuchur

2018-09-28 20:27:11
  • #1
Hello everyone,

I have here the payment plan of a general contractor (GU) for review. I would like to present the payment plan to you with the request for comments.

10% after completion of building application documents
65% on the 2nd day of construction, completion of the building shell, windows, doors, roof covered
15% 4 weeks after start of construction, completion of screed, underfloor heating, heating and sanitary piping
10% after acceptance

This is a large German general contractor; the basis is delivery ready for occupancy without any own contribution.

I know that the contract is not great from the client’s perspective. Especially considering that the general contractor reserves a construction period of 25 weeks from the start of construction, but already 90% is paid after 4 weeks (and the loan must already be serviced accordingly, while moving in is still far away).

However, one must also consider that a prefabricated house is largely prefabricated. When the building shell is up, significantly more is prepared in the walls than in a conventional solid construction shell.

Also, the willingness of the general contractor to accept changes to this will tend to zero. Nevertheless, the question: Is this still okay and usual or rather already a black sheep of the family?
 

Caspar2020

2018-09-29 07:13:00
  • #2


What else happens for such a long time?
 

Fuchur

2018-09-29 08:15:07
  • #3
Well, basically everything that still needs to be done between "Montage der Fertigwände" and "bezugfertig": screed drying, electrical installation, heating, floors, walls, painting, tiling, stairs,... just what comes to mind quickly.

That is a lot for 10% of construction costs including possible defect claims.

Maybe nothing happens for months either. The fact is, the general contractor reserves a construction period of up to 25 weeks from the start of assembly or from the completion of the basement.

If we take this further and assume that the construction loan is not taken out at a single bank, e.g. when using state funding or KfW, then by the second day of assembly you are already in the repayment phase for significant parts of the loan and are still paying rent on the side.
 

Knallkörper

2018-09-29 08:38:48
  • #4
I would definitely not sign that. Even the 10% for the application documents is not realistic, and it continues like that. 90% then are without electrical final installation, without sanitary fixtures and fittings, tiles and wall/floor coverings are missing. In other words, everything expensive is supposed to be covered by 10%. The services certainly lie in a value range of 30-50k. Besides, these are precisely the trades where mistakes happen, where sometimes the finish is off, or where the wrong material is accidentally used. I assume heating and ventilation are missing as well.

We had 15% open at the end, after completion of the house, until acceptance. That is of course relatively much, but for you it would be mathematically below zero. If you argue over defects after payment of the 90%, he will simply stop building, but wait and delay until you give in, e.g. because of the rent payments.
 

Fuchur

2018-09-29 08:54:29
  • #5
Yes, that was also my first impression. There is still the possibility to withhold 5% of the first installment according to the [Baugesetzbuch] until acceptance, which does not significantly improve the situation.

The basement and garage are carried out by third-party companies and must therefore be paid in full after completion.
 

tomtom79

2018-09-29 08:56:49
  • #6
Which company is that?
 

Similar topics
18.03.2015Developer information varies. What is the realistic construction time?19
30.04.2015KFW70 with gas-solar heating65
19.05.2015Heating children's room, bedroom, and bathroom14
27.07.2015New building heating?13
08.12.2015Payment plan: paid too much at the beginning?11
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
02.06.2016Necessary insurances during construction and afterwards11
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
11.06.2019Is there a warranty also on heating / air pump?13
22.03.2017Is a high first installment common in a payment plan?23
30.06.2018Construction contract - Uncertainty regarding payment schedule33
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
19.08.2018Strategically well-planned handover completion under building supervision11
23.10.2018Payment plan single-family house via general contractor - surprised17
23.09.2019Payment plan set up strangely?18
05.06.2019GÜ insolvent - and now? (Payment plan etc.)23
07.05.2019Payment plan - unreliable? Your assessment11
14.11.2021Sell an apartment from a two-family house immediately after completion34
31.01.2024Building with GU: Payment Plan and Guarantees18

Oben