Offset construction cost overruns against architect fees?

  • Erstellt am 2014-11-22 21:28:12

TESTUSER

2014-11-22 21:28:12
  • #1
Good day

We have recently moved into our newly built single-family house. The house turned out great, but the costs are much higher than calculated in the cost estimate. The cost overrun amounts to approximately CHF 270,000, which corresponds to 32.5%. Yesterday I received another invoice for just under 6,000, which of course is again not included in the estimate. Yesterday I lost my temper and I am wondering if I can offset this invoice with the outstanding fee from the architect. I think if he wants to take me to court, things do not look good for him due to the high cost overrun. It is of course important to mention that within this overrun only one item amounting to 5,000 was additionally desired by us... everything else are simply costs that the architect did not calculate or miscalculated.

What do you think about this? Thanks for any information.

Best regards Philippe
 

toxicmolotof

2014-11-22 21:40:29
  • #2
A construction cost volume of just under one million (800,000) is already substantial.

What generally bothers me: Barely any details, what cost how much more and what caused it? Extra requests/upgrades by the builder or volumes/measurements incorrect? Or costs per unit too low? Completely forgotten positions?

I mean, around 200K you usually don’t just miscalculate so easily.
 

lastdrop

2014-11-23 08:36:50
  • #3
And how much of the overrun was "intended" or approved by you?

By the way, I believe that a simple offset against the fee will not be possible, but I am not a lawyer.
 

Bauexperte

2014-11-23 12:11:13
  • #4
Hello Philippe,

Your description of the events is confused and incomplete; probably due to yesterday's excitement. Please try again with more detail. Thank you.


You should be very careful with this "assumption," because it can easily backfire!

Rhenish greetings
 

Similar topics
03.01.2016surprising bill, no cost estimate12
18.11.2016Electrician's invoice after 2.5 years - What are my rights?18
17.10.2011Need an invoice for an IKEA BESTÅ BURS TV bench21
28.03.2017Invoice land registry entry not for all buyers?13
18.08.2017First invoice for earthworks and base slab due25
19.10.2017Invoice from the notary - 4 days after the notarization appointment11
08.03.2018Invoice for water connection despite payment through property price?35
10.08.2018Landscaping company - defects, high bill, no warranty?!13
03.07.2025BG Bau is sending us a high bill - can I defend myself against it?14
11.03.2020Architects invoice - Amount okay?13
12.11.2020Craftsman invoice for replacement of defective tool27
22.01.2021The invoice contains unauthorized items, how should one proceed?13
02.02.2021The contractor wants to issue an invoice for planning services60
10.12.2021General contractor's offer vs. final invoice - a nightmare19
08.01.2025Problems with subcontractor's invoice19

Oben