need help with electrical installation

  • Erstellt am 2013-06-10 12:55:57

PearlJam1976

2013-06-10 12:55:57
  • #1
Hello dear experts in the forum!

We are currently having a terraced house built by a developer.

Interior walls are already plastered. Installation of the underfloor heating and the heating and sanitary fixtures is imminent. After that, the screed will be applied.

Regarding the electrical installation:
The developer standard was, of course, once again close to the minimal equipment according to DIN or RAL 1*.

For this reason, we had to pay an additional charge of nearly 8,000 EUR for various extra sockets, network cabling, and an 8-participant satellite system (5 users).

In the construction contract between the developer and the electrical company, an installation in conduit was clearly agreed upon. Also, when commissioning our special requests, formulations such as “satellite system from the attic to the basement in conduit” were used.

In retrospect, the electrical company found out that they did not install the system or did not do so continuously in conduit. They justified their approach with the “local customary installation” and also stated that even with conduit, no subsequent cable pulling is possible (with sheathed cables).

This manifests as follows (please also look at the pictures – the link is given below):
Installations on the concrete floor or in the concrete ceiling are in conduit up to just inside or in front of the brick walls. After that, the sheathed cable continues under the plaster to the boxes.

The Cat7 and coaxial cables were even laid correctly up to the boxes. However, the cables then lie partially bare (without conduit) in the riser to the basement, which was later bricked up and filled (no shaft!).

All walls are already plastered. The riser is bricked up per floor and the corresponding recesses in the concrete floors are concreted closed.

Opening the riser is, in the opinion of the involved companies, no longer possible because the risk of damaging the gas, water, and electrical lines is too great.

We were initially offered a compensation sum of a mere 300 EUR for this gross overall defect.

Now I am at the point with the developer and the electrical company that the following will be retrofitted at no cost to me:

Next to the original riser, a small shaft will be newly built in which a total of 5 empty conduits as reserve should run into various rooms or the attic.
The shaft will be visually inconspicuous, matched to the existing conditions, and plastered. The empty conduits will then be led over the raw floor to a location of my choice and later cut flush with the screed there.
This solution is intended to compensate for the missing replaceability of the Cat and coaxial cables.

Furthermore, the warranty for the cables in the riser will be extended from 5 to 10 years according to VOB.

The compensation sum was increased from 300 EUR to 600 EUR.

We are now willing to have the solution with the shaft and the empty conduits (reserve) implemented. We can also imagine the warranty extension.

However, the amount of the compensation payment is not comprehensible or acceptable to us.

We are of the opinion that there is a significant difference between the installation carried out and the intended installation (completely in conduit).

From our point of view, the following impairments must be permanently accepted by us and can no longer be corrected on site:

- Disadvantage compared to the other owners of the terraced houses. In their cases, installations were changed afterwards or carried out from the beginning, partly beyond the standard (in conduit with individual wires).

- Retrofitting of all cables is not possible because even cables laid in conduit up to the box are bricked in without conduit in the riser.
Costs, time, and material effort in the event of future damage or retrofit are significantly higher than in the other houses.

- Due to missing conduits and boxes in cast in-situ concrete walls during the shell construction phase (I have the work plans), installations are now located in places that we originally did not intend or plan.

- Due to partly sloppy installation and deviations from usual installation zones, there is a risk of future cable damage.

- Repairs in the riser (including gas and water) will only be possible in the future with great caution because the electrical cables were tied with cable ties on and between the water/heating pipes.

We would like to know your opinion on this topic.
We are especially interested in your assessment of a realistic compensation.
We are also interested in your general opinion on the quality of the installation.

Many thanks in advance for your comments and advice!

Regards
PearlJam1976
 

PearlJam1976

2013-06-13 07:41:40
  • #2
Hello!

No one has an opinion?

Regards
PJ1976
 

Bauexperte

2013-06-13 12:38:59
  • #3
Hello,

I really like Eddie Vedder's voice ;)


Unfortunately, there is not much to assess. In my opinion, there are only 2 options for you: either you come to an agreement with your contractor with the consequence of receiving less credit than perhaps the actual defect justifies, or you involve an expert specializing in electrical matters and let it come to a legal dispute. In the latter case, you should keep in mind that this will be a lengthy process and implies the possibility – as unfortunately is often the case – of throwing good money after "bad" money :(

You have signed a work contract, and it certainly contains references to the Building Code/the VOB, regarding how to proceed in cases of defects. The problem is – actually winning in court here is a difficult endeavor because what is right in the eyes of the builder and what is right in the eyes of the contractor are generally two different things. The judges rarely have time and even less inclination to deal with these comparatively minor matters (dispute values in the range of €0-2K) and therefore usually recommend a settlement. By the way, even regional courts (dispute values from €10K) tend to settle. The consequence – even if you were to be credited with more money: your lawyer will bill twice (allowed to do so), you pay the proportional costs of the court-appointed expert (added in the legal dispute), and the court costs are shared in proportion to the disputed amount. In the end, less remains of a supposedly higher amount won than if you had agreed with your contractor from the start.

Rhineland regards
 

PearlJam1976

2013-06-13 12:53:15
  • #4
I also believe that the most undisputed thing about the whole matter is Eddie's voice :D
 

Similar topics
17.01.2021Installation of a satellite system38
02.06.2016Conduit Costs - Network, SAT, Backup14
04.01.2017House wiring LAN/SAT62
09.06.2017What is a realistic price for a SAT system including installation?45
21.09.2017Electrical planning - How many sockets are enough?120
28.04.2024Potential equalization for satellite must be laid separately17
08.05.2019SAT system in new construction: Unicable or star wiring?41
29.02.2020Implement LAN and SAT in a single-family house with a central server cabinet40
17.11.2019Satellite system - buying guide and installation41
09.09.2019Are empty conduits and empty boxes in WU concrete dangerous?10
16.10.2019Rent for construction dryer in final invoice/builder - legal?14
08.01.2021Are LAN sockets still up-to-date? WLAN/wireless is the future!262
08.04.2021Building without antenna and SAT-CAT cable without conduit?65
09.06.2020False statement by sales partner at developer12
27.06.2020Trades do not provide defect remediation with the developer10
26.01.2021Reasonably changing existing SAT/cable connection botch work27
25.03.2021Leading pipes from the house into the garage14
04.07.2022Conduits for SAT and TK, mandatory or not in new construction?13
22.12.2024Floor plan changes for end-terrace house from the developer133

Oben