Likee68
2022-08-13 15:15:19
- #1
Hello everyone!
My wife and I are currently looking for a house construction company and have received a sample contract from our favorite - a smaller, local provider.
It concerns the wording in the contract:
EXCERPT:
§2 Remuneration
Lump sum contract:
A lump sum price of €510,204.00 gross (before discount), in words: five hundred ten thousand two hundred four euros, is agreed upon as remuneration. The blue-highlighted positions from own work according to the Excel list are not included in the amount.
§3 Labor and material price adjustment clauses
Labor and material price adjustment clauses (material and transport adjustment clauses) are agreed upon as follows. In the event of price changes in material procurement > 20%, the affected services must be renegotiated. The agreed prices are – except for § 2 para. 3 VOB/B and other price adjustment possibilities provided for in the VOB/B as well as those resulting from general legal principles – fixed prices.
I view the wording very critically:
I would prefer to have a legal contract review carried out.
Do you also see these wordings critically?
I am grateful for any constructive response!
Did you have similar wording in your contract?
My wife and I are currently looking for a house construction company and have received a sample contract from our favorite - a smaller, local provider.
It concerns the wording in the contract:
EXCERPT:
§2 Remuneration
Lump sum contract:
A lump sum price of €510,204.00 gross (before discount), in words: five hundred ten thousand two hundred four euros, is agreed upon as remuneration. The blue-highlighted positions from own work according to the Excel list are not included in the amount.
§3 Labor and material price adjustment clauses
Labor and material price adjustment clauses (material and transport adjustment clauses) are agreed upon as follows. In the event of price changes in material procurement > 20%, the affected services must be renegotiated. The agreed prices are – except for § 2 para. 3 VOB/B and other price adjustment possibilities provided for in the VOB/B as well as those resulting from general legal principles – fixed prices.
I view the wording very critically:
[*]From which baseline is the percentage increase calculated? If the prices in the fixed price were deliberately calculated too low, one would immediately exceed the 20% threshold when compared with the correct prices.
[*]Only increases are renegotiated, but not discounts?
[*]What does renegotiate mean? In case of a construction stop, the contractor could put us under extreme pressure and negotiate in his favor. A predefined procedure would be better in this case.
[*]At the end, there is also a reference to all other possible price increase options, which is very non-transparent to me again...
I would prefer to have a legal contract review carried out.
Do you also see these wordings critically?
I am grateful for any constructive response!
Did you have similar wording in your contract?