Hello everyone,

we have decided on a construction company that will build a turnkey house for us on our property. So far, the company has made a good impression. Only with the payment schedule we are not sure if it is okay, as we have no experience with this at all? The payment schedule:

3% after receiving the order confirmation
5% after completion of the planning submission
7% after the start of earthworks
15% after completion of the ceiling above the basement/cellar
15% after completion of the ceiling above the ground floor
10% after raising the roof truss
10% after the start of window installation
15% after completion of the interior plaster
5% after screed installation
5% after the start of tiling work
10% upon acceptance

Is this okay or do you see any problematic amounts or timing? Thanks in advance!
 

goalkeeper

2019-07-20 17:35:18
  • #2
From my feeling, the house is overpriced in every section. You have already paid over 60% of the house before the windows are even in. That may not necessarily be bad - if the company goes bankrupt, then you have a problem.
 

Yosan

2019-07-20 18:09:17
  • #3
I find this "after the start..." strange. For us, everything is "after completion..."
 

Müllerin

2019-07-20 19:13:07
  • #4
3% after receipt of the order confirmation
5% after completion of input planning
7% after start of earthworks

are 15% without anything visible from the house

15% after completion of the ceiling above the basement/cellar
15% after completion of the ceiling above the ground floor
10% after erection of the roof structure

are 55% without a sealed roof

10% after start of window installation

are 65% and the house is still not sealed. "Start" can mean one window is in, the rest not yet...

15% after completion of interior plaster

that’s already 80% !!
And there is still quite a bunch missing.

5% after screed installation
5% after start of tiling work

10% with the acceptance
that’s ok

They won’t do more? What about electrical + sanitary?
I don’t read anything about painter/flooring, are you doing that yourselves?
 

ypg

2019-07-20 19:48:31
  • #5


That is very often the case and not unusual that not every trade is mentioned.
The more detailed, the better, but as already said: it is very often like that. Also that you pay more than 50% for a tight house.
For planning etc., 5-10% is okay.

Some small things like the ones already mentioned would also bother me.
However, the payment schedule is usually notarized by the companies. You can't just change anything like that easily. That can have devastating consequences for a company.
 

Mottenhausen

2019-07-21 00:21:11
  • #6
Is there even the possibility of negotiating the contract and the payment plan? Overall, I would prefer to focus on clauses like "assignment of the loan disbursement," "assignment of the instruction for disbursement," "assignment" of the house rights," etc. The payment plan is a topic of its own, since even the completion of a trade is never clear-cut. Is the window installation only completed with the final adjustment of the opening mechanism before handover? Not to mention the "start." The best payment plan is useless if the construction company can request money from your loan at the bank at will and it then flows directly into their account.
 

Similar topics
26.09.2013What do you think of this payment plan?, Property appraisal18
08.12.2015Payment plan: paid too much at the beginning?11
26.02.2016Renegotiation of payment plan, please help25
01.08.2017Questions about the payment plan10
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
28.02.2017Are securities customary for completion and warranty?24
22.03.2017Is a high first installment common in a payment plan?23
17.07.2017Payment plan okay - 13% after the floor slab?21
30.06.2018Construction contract - Uncertainty regarding payment schedule33
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
30.09.2018Payment Plan for Prefabricated House - Reviews and Experiences Desired10
23.10.2018Payment plan single-family house via general contractor - surprised17
23.09.2019Payment plan set up strangely?18
07.05.2019Payment plan - unreliable? Your assessment11
02.02.2020Payment plan (Broker and Developer Regulation) and Developer's payment plan10
20.02.2020Is the payment plan okay?10
11.12.2020Payment plan and unpleasant feeling11
16.04.2021Wood price increase - order confirmation already signed25
29.02.2024Payment plan - 5% retention not regulated11
11.07.2024Payment plan for shell construction - market-oriented?17

Oben