lechon
2012-10-17 14:00:05
- #1
Hello house construction forum users,
we are about to finalize with a general contractor (small developer) and have now received the payment plan. In my opinion, the payments are somewhat premature compared to the realtor and developer regulations.
What do you think? Can anyone give me a tip?
5 % after handing over the building application documents
(after individual planning, building regulations pre-approval, completion of the building application and drainage drawing)
4 % after receipt of the building permit
(incl. approval of the drainage drawings)
14 % after completion of the base
(incl. completion of the basic pipelines, earthworks in the base area, creation of foundations and Thermobodenplatte)
15 % after completion of the reinforced concrete ceiling above the ground floor
(incl. completion of the shell walls ground floor)
18 % after erecting the roof structure
(incl. lathing and installation of the underlay membrane)
21 % after installation of windows and exterior doors
(incl. completion of the shell walls attic)
7 % after predominant completion of the interior plastering
(incl. rough electrical installation)
10 % after laying the screed
(incl. laying moisture barrier and screed insulation as well as rough heating installation)
2 % after predominant laying of the tiles
(without skirting boards in the area of the interior doors)
2 % after installing the staircase
2 % after final acceptance
(and installation of the interior doors)
_______
100 %
Thank you very much for your help!
we are about to finalize with a general contractor (small developer) and have now received the payment plan. In my opinion, the payments are somewhat premature compared to the realtor and developer regulations.
What do you think? Can anyone give me a tip?
5 % after handing over the building application documents
(after individual planning, building regulations pre-approval, completion of the building application and drainage drawing)
4 % after receipt of the building permit
(incl. approval of the drainage drawings)
14 % after completion of the base
(incl. completion of the basic pipelines, earthworks in the base area, creation of foundations and Thermobodenplatte)
15 % after completion of the reinforced concrete ceiling above the ground floor
(incl. completion of the shell walls ground floor)
18 % after erecting the roof structure
(incl. lathing and installation of the underlay membrane)
21 % after installation of windows and exterior doors
(incl. completion of the shell walls attic)
7 % after predominant completion of the interior plastering
(incl. rough electrical installation)
10 % after laying the screed
(incl. laying moisture barrier and screed insulation as well as rough heating installation)
2 % after predominant laying of the tiles
(without skirting boards in the area of the interior doors)
2 % after installing the staircase
2 % after final acceptance
(and installation of the interior doors)
_______
100 %
Thank you very much for your help!