BenutzerPC
2018-07-26 17:31:17
- #1
Can the measurement for the kitchen be done already after the completion of the interior plaster and without screed? Background: The kitchen has a delivery time of about 12 weeks after ordering. We want to save time accordingly. Currently, it otherwise looks like the kitchen is the only reason why we cannot move in. Our site manager said that he recommends taking the measurement at least after the interior plaster. The screed is not so relevant, as the height can also be read from the plans. What is your opinion on this?