Introduction and first question!

  • Erstellt am 2014-04-19 20:22:17

athuro

2014-04-19 20:22:17
  • #1
Hello everyone, I would like to introduce myself before my first question. My name is Athuro and I live with my wife and our children in Hamburg. We are about to start building our single-family house (without a basement) in Bauhaus style and are facing an important decision. Two days ago, we had an appointment with the surveyor and our general contractor's site manager. The height of the finished floor (top edge of the finished floor) was defined in relation to the center of the street. The street is slightly sloping, meaning at the higher end we would be 20 cm above the street, and at the lower end about 38 cm above the street, always referring to the top edge of the finished floor. The garage at the lower end would stand slightly lower than the house because it is not allowed to be built higher than 2.75 m due to the boundary construction. My question is: Is 20 cm enough for the house? It would be nice because the plot slopes to the back as well, and otherwise we would have problems with garden landscaping, but the most important thing for me is a permanently dry house (foundation). If I understood the site manager correctly, then the ground/foundation will probably be constructed as follows: floor - 17 cm screed - 20 cm base slab - 10 cm insulation - approx. 80 - 100 cm sand. The thickness of the base slab might be slightly increased because the structural engineer still wants to wait for a second soil report. I hope I was able to express myself somewhat clearly, and I hope you have an idea about this. Best regards and happy Easter [Athur0]
 

nordanney

2014-04-19 20:55:39
  • #2
It is the same with us, our finished floor level is also "only" 20" cm above street level. Everything is properly sealed and has been working without any problems so far.
 

Bauexperte

2014-04-20 11:49:57
  • #3
Hello Athuro,


Why 20 cm? Is this already the result of the weighted average or does it still need to be calculated from both values? Then the house would stand 29 cm “high” in the middle and then less towards the higher and lower ends. And why is this average determined on the property and not in the construction plan discussion before the start of construction?


20 cm means roughly one step; that is enough to lead water away from the house, i.e. past the floor slab.


The construction manager certainly mentioned gravel or crushed stone; sand would be bad because it is not load-bearing ;) Why a second soil report?

Regards from the Rhineland
 

athuro

2014-04-21 03:06:07
  • #4
: many thanks for the quick response! @ Building expert: the angle brackets are now all at the top edge of the finished floor, 20 cm above street level, measured at the highest point of the street. If I understood correctly, the top edge of the finished floor, as you described, is 38 cm above the street at the lower end of the house and 29 cm in the middle. On-site appointment, because we wanted to assess the entire site at once, as we want to have a lowered living area at the back. Now you are making me a little worried: I am pretty sure about the sand, but I also read something about a fine grading by the earthworks contractor! Can that work well with good compaction? Unfortunately, I realized too late that a studded membrane is supposed to be used as a cleanliness layer! Does that work in combination with the insulation? Or is it better to accept extra costs for concrete? 2. Soil report because the first one was done before the demolition, and now more points should be measured, but it is included in the price, so no price gouging! Many thanks for the effort, best regards from the North
 

Similar topics
14.08.2012Build a home? Land in prospect19
24.07.2014Soil assessment report, filling - additional costs?11
15.12.2016Top edge of finished floor and road construction height: poorly planned?21
14.11.2016Bathroom ventilation drips despite pipe insulation10
31.07.2019Filling and compacting the ground for the house155
19.04.20172.25m below street level - Cost estimation14
16.07.2017Plot with terrain drop - separating wall neighbors - foundation?44
23.08.2017Our house, a massive city villa, was planned in depth18
10.06.2021Optimal height of finished floor level to street edge75
30.05.2018Base plate on the top edge or bottom edge? Who has experience?10
25.06.2018Heat pump foundation too close to garage, repair or new construction?10
04.03.2019No stopping zone in front of the property11
01.06.2019Bending-resistant base plate driven over by truck in less than 1 day23
19.11.2019Preliminary contract for land due to soil survey17
11.05.2021Neighbor is building a retaining wall on my property. What should I do?87
13.06.2022Should the land be filled up or not?87
01.05.2021Property with expansion house experiences14
03.06.2021Property purchased - start construction planning before handover?11
20.04.2022Foundation positioned incorrectly, what to do?24
16.12.2022Forgot insulation on the dormer wall - mold on wood - what to do?13

Oben