I'm not a professional myself, but that's what I was told.

1. When in addition to the frost skirts a soil replacement must take place.
2. When building on a gentle slope and several sides of the frost skirt remain partially visible.

Of course, this means you can't pour concrete against earth.
 

Wassermann

2022-03-24 07:06:31
  • #2
As far as I know, every professional advises against pouring the skirts and the base slab simultaneously.
 

TmMike_2

2022-03-24 07:40:44
  • #3
Good, that's clear. In our area, we have sand/gravel, only topsoil is removed and refilled with fill sand and compacted.
 