How to clad a projecting plinth (facade-basement wall)

  • Erstellt am 2020-08-18 13:14:21

K1300S

2020-08-19 15:33:13
  • #1
Uh, you mean the planning has not been done before the start of construction execution? That would be grossly negligent. But if there is such a planner: Give him your task and wait for his response.
 

Tamstar

2020-08-19 15:59:14
  • #2
have you already started building? I had the impression that you haven't started yet, but I haven't looked through the history either. Do you know how high the sealing will be pulled up?
 

11ant

2020-08-19 16:41:19
  • #3

That means the problem doesn't even exist yet!!!???
Well, then he should just plan away the stupid base overhang again and the problem won't arise at all.
 

annab377

2020-08-21 10:29:27
  • #4
No, we have not started yet and the base theme thus came before the start of construction on the table.
 

vanny2705

2020-08-21 10:40:27
  • #5

That's already good! What does the architect/site manager say?
Attached is a sketch that sounds/looks more logical to me:
 

annab377

2020-08-21 10:56:58
  • #6
The structural engineering office is still on vacation for about two weeks. I was just thinking about it myself and wanted to hear your opinion.

Thanks for your drawing. What advantage does the smaller Ytong block bring? Why not like this?
 
Oben