How strictly must developers adhere to the site plan?

  • Erstellt am 2021-03-17 16:46:32

Dude2000

2021-03-17 16:46:32
  • #1
Before purchasing the house, we received a site plan on which certain items were marked as "demolition." How must the developer adhere to this?
 

Osnabruecker

2021-03-17 17:09:53
  • #2
As contractually agreed. Without more information, no assessment is possible.
 

11ant

2021-03-17 17:15:55
  • #3
Are you referring to a brochure of the planned land development? The developer must only adhere to what is stated in the purchase contract with you. Towards the building authority, he must demolish what he has been authorized to demolish (and ensure the structural stability of what he has applied to retain). Example: Furniture store is demolished, investor builds a dozen semi-detached houses on the entire campus, hall is demolished, one hall wall remains standing as a screen towards the neighboring mixed-use area. Daily routine, completely fine if application and execution are congruent. Sketches are common in building applications, but not excluded in demolition applications either.
 

Dude2000

2021-03-17 18:23:36
  • #4
Yes, the site plan that has been submitted, which states what will be demolished and what will remain.
 

icandoit

2021-03-17 18:34:49
  • #5
Then show the plan and the differences in it. So we also know what it is about. You have a knowledge advantage. We cannot look into your head.
 

Dude2000

2021-03-17 19:10:08
  • #6
The yellow above is the wall The street is therefore narrower, which also belongs to the property, so the marked flowerbed and the trash bin space do not exist. Now it is more like this
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
26.09.2011Finding tiles from other manufacturers / sample selection for builders13
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
16.07.2012The builder "outsources" fixed-price services to subcontractors12
03.08.2012Contract Supplement to the Construction Contract by the Developer36
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
18.02.2014Massive problems with the builder - is contract termination possible?33
23.06.2014Developer charges heavily for replanning - justified?12
08.10.2014How do you search for a suitable property developer?30
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
01.03.2015The developer does not build according to the plan14
15.04.2015Duplex construction: Joint or separate developer?20
13.06.2015New construction with developer / construction drawing documents23
09.09.2015Buy land separately from the developer13
24.12.2015Single-family house, Energy Saving Ordinance 2016, developer recommends additional insulation - is it sensible?39
15.03.2016Developer changes plot size25
16.03.2016Single-family house - developer rejected25
11.07.2016Question about site plan - is a 3m distance mandatory?12

Oben