I wouldn't call it crazy. Groundbreaking at the end of February, moving in mid-October. Basement, solid construction. Including ~ 6 weeks of standstill due to problems with multi-utility coordination and subsequent summer holidays. There was still room for improvement. The team from is also setting a good pace.
We actually had no standstill at all or I was partly at the construction site until 1 a.m. to get things done...and still we ended up at 51 weeks