How long does it approximately take from the start of planning until approval?

  • Erstellt am 2020-05-08 08:21:23

frsytiwo

2020-05-08 08:21:23
  • #1
We are still at the very beginning and have already purchased our plot of land. We are currently creating our first floor plans for our single-family house. How long does it approximately take to get the building permit? We want to build turnkey with a general contractor; how much time does a company need to present us with an offer?
 

Pierre

2020-05-08 08:27:06
  • #2
Should the crystal ball be unpacked here now?

How on earth are we supposed to know how long you will need from completing your floor plans until submitting the building application?
 

Lumpi_LE

2020-05-08 08:39:21
  • #3
Depends on many variables. Do you also want the planning to be done by the GU? Then one can roughly assume that it will take 2-3 months to find a suitable one. They will then complete the GP in 2-3 months. Depending on the location, it will take another 2-5 months until it is approved. Construction usually will not start earlier than 12 months after the contract is signed. Ergo building permit before Christmas or only in spring 2021. Construction start autumn 2021. Roughly for orientation.
 

frsytiwo

2020-05-08 08:58:22
  • #4
Thank you for the timeline. We just want to know roughly how long one should plan for it.
 

nordanney

2020-05-08 09:08:17
  • #5
Don't ask us. Ask yourself how quickly you finish your planning. If you take a standard house, you can sign the contract with the general contractor on Monday so that they submit the building application. With exemption from approval (e.g. NRW) you don't even need a building permit. But I would also reckon with at least one year until the excavator starts moving.
 

Tassimat

2020-05-08 09:10:23
  • #6
Just ask him...
 

Similar topics
31.10.2008Is a building permit also required for a carport and equipment shed?13
15.02.2011Building permit application12
27.09.2018Cost of building permit in exemption procedure, new construction11
19.03.2015Questions about the building permit21
28.11.2024Neighbor's lawsuit against approved building permit46
18.03.2016Influence of the neighbor in building permit18
16.01.2017No building permit as long as the land is not developed?10
20.08.2017Issuance of the building permit?24
31.12.2017Winter garden conversion - building permit required or permit-free?15
08.01.2018According to the law, the building permit is automatically granted if12
22.01.2018Building on still foreign land - Waiting for building permit25
21.06.2018What must be included in the building permit? Legal certainty?19
29.08.2018Filling up a raised plot of land to make it level - building permit required?16
18.09.2018Immission protection concerns self-service gas station - building permit?20
24.10.2018Broker sells house without current building permit. Notary costs?25
26.01.2019Building permit from 1931 not adhered to35
08.04.2019Can the garage be moved after obtaining the building permit?11
09.09.2022Experiences with forest conversion in the context of building permits in Brandenburg20
28.08.2019Building permit for terrace roofing14
06.09.2019Construction project and building permit feasible?97

Oben