Hello everyone,
how is the sealing of a parapet actually done if a railing is to be mounted on it? I started drawing as follows:
[ATTACH alt="attika.jpg" type="full"]39470[/ATTACH]
On the Ytong stone, there should presumably be a concrete frame (which should possibly be 10 or 15cm high) in order to mount the railing on it. How is the sealing done here approximately? Do you then drill into the sheet metal later (unless you possibly use a granite slab with a slight inward slope instead of sheet metal)?
how is the sealing of a parapet actually done if a railing is to be mounted on it? I started drawing as follows:
[ATTACH alt="attika.jpg" type="full"]39470[/ATTACH]
On the Ytong stone, there should presumably be a concrete frame (which should possibly be 10 or 15cm high) in order to mount the railing on it. How is the sealing done here approximately? Do you then drill into the sheet metal later (unless you possibly use a granite slab with a slight inward slope instead of sheet metal)?