Sandra.M85
2022-09-14 22:04:47
- #1
Hello,
during the construction of our single-family house (approx. 130 sqm area), the screed was poured 2 weeks ago.
Our general contractor now presents us with the following choice:
1) Heating the screed (= cement screed) with a 19 kW heating device, starting in 10 days.
2) Heating the screed using underfloor heating operated by a heat pump from the installation of the heat pump in mid-October.
Our contract states that I pay for the heating costs, and that the general contractor pays for the construction electricity.
Completion of the house is according to the contract February 2023.
Option 1: According to the general contractor, I have to pay for the construction electricity for the heating device, as it counts as heating costs.
So far, I assumed that heating costs are costs so that the workers can work, but not costs for heating the screed.
If I favor option 1, I will have to bear these costs anyway, since the general contractor will also be finished in February with the cheaper option 2.
How expensive would solution 1 be for me? How expensive is construction electricity and how much do I need to operate the heating device until the screed is dry?
According to the general contractor, I can move in this year with option 1, so I probably save 1 month’s rent for the current rental apartment, i.e., about 650 euros, and avoid the risk that option 2 entails, namely that the heat pump might still not be installed by mid-October.
Option 2): If after installation of the heat pump in mid-October the heating takes place via underfloor heating, does the general contractor have to pay for the electricity required for this? Would this still run via the construction electricity meter (construction electricity is paid by the general contractor according to the contract) or already via my new private electricity meter?
How much electricity would be needed here for heating and how high would the estimated savings be compared to option 1, if I have to pay for this electricity?
Which option would you choose?
during the construction of our single-family house (approx. 130 sqm area), the screed was poured 2 weeks ago.
Our general contractor now presents us with the following choice:
1) Heating the screed (= cement screed) with a 19 kW heating device, starting in 10 days.
2) Heating the screed using underfloor heating operated by a heat pump from the installation of the heat pump in mid-October.
Our contract states that I pay for the heating costs, and that the general contractor pays for the construction electricity.
Completion of the house is according to the contract February 2023.
Option 1: According to the general contractor, I have to pay for the construction electricity for the heating device, as it counts as heating costs.
So far, I assumed that heating costs are costs so that the workers can work, but not costs for heating the screed.
If I favor option 1, I will have to bear these costs anyway, since the general contractor will also be finished in February with the cheaper option 2.
How expensive would solution 1 be for me? How expensive is construction electricity and how much do I need to operate the heating device until the screed is dry?
According to the general contractor, I can move in this year with option 1, so I probably save 1 month’s rent for the current rental apartment, i.e., about 650 euros, and avoid the risk that option 2 entails, namely that the heat pump might still not be installed by mid-October.
Option 2): If after installation of the heat pump in mid-October the heating takes place via underfloor heating, does the general contractor have to pay for the electricity required for this? Would this still run via the construction electricity meter (construction electricity is paid by the general contractor according to the contract) or already via my new private electricity meter?
How much electricity would be needed here for heating and how high would the estimated savings be compared to option 1, if I have to pay for this electricity?
Which option would you choose?