Redsonic
2018-01-04 23:39:48
- #1
Hello everyone,
I have a question regarding the final installment for my newly built single-family house. The contract states the following:
"The client must provide a security for the timely completion of the work without significant defects in the amount of 5% of the remuneration claim upon the first installment payment. (...) The security can be provided by a guarantee or another payment promise (...)."
I have a bank guarantee for 5% of the construction sum.
In the payment plan, the 13th payment of 2% is stated as "after acceptance and rectification of significant defects that prevent moving in."
The acceptance took place on 21.12.2017, my move-in immediately thereafter. The acceptance protocol includes various open items, but none of them constitute significant defects. Some items are still not completed.
The construction company has now proposed withholding 2,000 EUR due to weather-related delay of laying the floor for the house entrance platform.
The truly significant missing items are however the following: balcony wood covering missing, exterior facade plaster with defects in the entrance area, usable standing height in the attic too low (a discount of 500 EUR was offered), some issues with electrical and painting work, entrance platform, dispute about balcony drainage through the platform...
The request to return the bank guarantee has already been made.
Can I now withhold an arbitrary amount or not since these are not significant defects? My idea would be to withhold the entire 2%. That would be 6,000 EUR. But would I then maybe face a payment lawsuit or would they stop the rectification work?
Best regards, Redsonic
I have a question regarding the final installment for my newly built single-family house. The contract states the following:
"The client must provide a security for the timely completion of the work without significant defects in the amount of 5% of the remuneration claim upon the first installment payment. (...) The security can be provided by a guarantee or another payment promise (...)."
I have a bank guarantee for 5% of the construction sum.
In the payment plan, the 13th payment of 2% is stated as "after acceptance and rectification of significant defects that prevent moving in."
The acceptance took place on 21.12.2017, my move-in immediately thereafter. The acceptance protocol includes various open items, but none of them constitute significant defects. Some items are still not completed.
The construction company has now proposed withholding 2,000 EUR due to weather-related delay of laying the floor for the house entrance platform.
The truly significant missing items are however the following: balcony wood covering missing, exterior facade plaster with defects in the entrance area, usable standing height in the attic too low (a discount of 500 EUR was offered), some issues with electrical and painting work, entrance platform, dispute about balcony drainage through the platform...
The request to return the bank guarantee has already been made.
Can I now withhold an arbitrary amount or not since these are not significant defects? My idea would be to withhold the entire 2%. That would be 6,000 EUR. But would I then maybe face a payment lawsuit or would they stop the rectification work?
Best regards, Redsonic