Handling the final installment for a single-family house

  • Erstellt am 2018-01-04 23:39:48

Redsonic

2018-01-04 23:39:48
  • #1
Hello everyone,

I have a question regarding the final installment for my newly built single-family house. The contract states the following:

"The client must provide a security for the timely completion of the work without significant defects in the amount of 5% of the remuneration claim upon the first installment payment. (...) The security can be provided by a guarantee or another payment promise (...)."

I have a bank guarantee for 5% of the construction sum.

In the payment plan, the 13th payment of 2% is stated as "after acceptance and rectification of significant defects that prevent moving in."

The acceptance took place on 21.12.2017, my move-in immediately thereafter. The acceptance protocol includes various open items, but none of them constitute significant defects. Some items are still not completed.

The construction company has now proposed withholding 2,000 EUR due to weather-related delay of laying the floor for the house entrance platform.

The truly significant missing items are however the following: balcony wood covering missing, exterior facade plaster with defects in the entrance area, usable standing height in the attic too low (a discount of 500 EUR was offered), some issues with electrical and painting work, entrance platform, dispute about balcony drainage through the platform...

The request to return the bank guarantee has already been made.

Can I now withhold an arbitrary amount or not since these are not significant defects? My idea would be to withhold the entire 2%. That would be 6,000 EUR. But would I then maybe face a payment lawsuit or would they stop the rectification work?

Best regards, Redsonic
 

bau.mal

2018-01-05 00:20:35
  • #2
Let me guess, you saved the money for external construction supervision in favor of a nice to have?


Says it all, really. Because


did not oppose the acceptance (confirmed in writing by you), since you finally wanted to move into the new house?


You would have had to record that in writing in the acceptance protocol. Now the opportunity has passed.
 

Redsonic

2018-01-05 00:24:06
  • #3
No, a building savings contract was available and included at the acceptance. He just said I should recalculate what all that is worth and then withhold up to 5% of the building amount.
 

HilfeHilfe

2018-01-05 08:45:03
  • #4
well, your house builder seems to be accommodating. we have paid everything out to be entered in the land register. the defects were successively addressed
 

Knallkörper

2018-01-05 19:42:43
  • #5
Reduction of the price by a reasonable amount. According to prevailing case law, reasonable is up to 2.5 times the cost of remedying the defect. 2000 is probably a bit too little. Then he won't do anything anymore and will forgo the few bucks.
 

Bieber0815

2018-01-05 23:31:34
  • #6
It is a tricky thing with the experts. Isn't that his job? Did you note the reservation in the protocol during the acceptance?
 

Similar topics
10.08.2018Landscaping company - defects, high bill, no warranty?!13
18.10.2018Liability for various defects after acceptance of the property19
21.05.2019Balcony door and window sills - defects in new construction28
21.08.2019Blocked account/bank guarantee as security for the municipality23
12.08.2019Relation Construction sum / Financing - Survey24
09.03.2021Withholding payment for defects in the shell construction74
24.12.2021GU insolvency after acceptance - Open defects15
03.10.2022Building acceptance of new construction despite missing heat pump. Significant defects?50
06.04.2023Deficiencies in the new construction. Dispute over the amount of withholdings.35
19.04.2024Bank withdraws financing commitment due to defects20

Oben