allstar83
2023-02-08 11:39:40
- #1
Hello everyone,
unfortunately, at the end of the house construction, an unpleasant issue was noticed. The right half of the roof does not drain as planned in the drainage plan via the cistern but directly into the sewage shaft which is about 2m in front of it. The general contractor was there, and the excavator driver reportedly said that at the time, they could not dig deeper due to the boundary/foundations of the neighbor. Apparently, the slope of the drainage was not sufficient to reach the cistern because of this.
Personally, this really bothers me now because we installed an expensive cistern, have a large roof, and could really use the rainwater in the garden. The construction manager is now explicitly checking the heights again – but I am not sure if it might still work.
-->My question is, however, what claims/what amount can we assert if this can no longer be remedied?
among others through
I still have a retention and have set a deadline for remediation. So far, all defects have been remedied by the general contractor without objection, and I continue to strive for a cooperative relationship with the general contractor even during the warranty phase.
Thank you very much
unfortunately, at the end of the house construction, an unpleasant issue was noticed. The right half of the roof does not drain as planned in the drainage plan via the cistern but directly into the sewage shaft which is about 2m in front of it. The general contractor was there, and the excavator driver reportedly said that at the time, they could not dig deeper due to the boundary/foundations of the neighbor. Apparently, the slope of the drainage was not sufficient to reach the cistern because of this.
Personally, this really bothers me now because we installed an expensive cistern, have a large roof, and could really use the rainwater in the garden. The construction manager is now explicitly checking the heights again – but I am not sure if it might still work.
-->My question is, however, what claims/what amount can we assert if this can no longer be remedied?
among others through
[*]Lost rainwater (I have installed an irrigation system)
[*]Higher drainage fees due to discharge directly into the sewer instead of via the cistern
[*]etc.
I still have a retention and have set a deadline for remediation. So far, all defects have been remedied by the general contractor without objection, and I continue to strive for a cooperative relationship with the general contractor even during the warranty phase.
Thank you very much