chrisw81
2019-05-15 15:27:39
- #1
Hello,
we have the following problem with our new building: in the shower of the guest WC on the ground floor, a vertical pipe shaft is planned to lead the wastewater from the upper floor downwards. The pipe shaft is located right near the entrance, and we would therefore prefer not to have it in that spot.
Now to the options I see:
A) A suggestion from the sanitation company was to relocate the pipe shaft next to the WC, where there is also a breakthrough in the floor, and then drain the water there. However, the pipe would have to be led from the original opening under the wall to the new location of the pipe shaft. This would be done either in the shower or in front of it (see option 1 and 2).


Now I wonder, does it make sense to do it this way and then lower the ceiling to hide the pipe? The ceiling height would then decrease from 2.6 m to about 2.45 m! But you could also integrate spotlights well, etc. However, what about steam/water in the cavity, etc.?
B) An alternative that occurred to me would be to relocate the pipe shaft in the shower to the other wall. There you could then build a pre-wall containing the pipe shaft. The size of the shower would then decrease, but that is okay. (see option 3). The question is whether the water from the pipe shaft can then be led under the shower tray to the original drain...

What do you think?
I look forward to your opinions.
we have the following problem with our new building: in the shower of the guest WC on the ground floor, a vertical pipe shaft is planned to lead the wastewater from the upper floor downwards. The pipe shaft is located right near the entrance, and we would therefore prefer not to have it in that spot.
Now to the options I see:
A) A suggestion from the sanitation company was to relocate the pipe shaft next to the WC, where there is also a breakthrough in the floor, and then drain the water there. However, the pipe would have to be led from the original opening under the wall to the new location of the pipe shaft. This would be done either in the shower or in front of it (see option 1 and 2).
Now I wonder, does it make sense to do it this way and then lower the ceiling to hide the pipe? The ceiling height would then decrease from 2.6 m to about 2.45 m! But you could also integrate spotlights well, etc. However, what about steam/water in the cavity, etc.?
B) An alternative that occurred to me would be to relocate the pipe shaft in the shower to the other wall. There you could then build a pre-wall containing the pipe shaft. The size of the shower would then decrease, but that is okay. (see option 3). The question is whether the water from the pipe shaft can then be led under the shower tray to the original drain...
What do you think?
I look forward to your opinions.