Alicante
2013-04-22 20:30:06
- #1
Hello everyone,
we would work with a general contractor. We are buying the land directly from the owner and then building with the general contractor. He proposes the following payment plan based on the real estate agent and developer ordinance (the contract only comes into effect with the building permit or an existing development plan):
1. Payment installment before planning 9%
2. Payment installment after demolition/clearing 5%
3. Payment installment after setting up the construction site and completion of earthworks 11%
4. Payment installment after completion of the foundation slab 7%
5. Payment installment after completion of the basement ceiling 6%
6. Payment installment after completion of the ground floor ceiling 6%
7. Payment installment after completion of the upper floor ceiling 6%
8. Payment installment after completion of the shell construction 9%
9. Payment installment after completion of carpentry work 3%
10. Payment installment after completion of roofing work 3%
11. Payment installment after installation of the windows 8%
12. Payment installment after completion of rough installation 7%
13. Payment installment after completion of interior plastering 9.5%
14. Payment installment after completion of screed 7%
15. Payment installment after acceptance, rectification of residual defects, and readiness for occupancy 3.5%
What do you think?
We were concerned because after the screed not much is left open, but sanitary, doors, tiles, etc. are still missing.
The general contractor explained to us that we never have to make advance payments.
The costs for electrical work, heating work, sanitary installations, interior stairs, doors, access paths, and tiles are included in payments 12–14. The exterior plaster is included in the interior plaster work at point 13.
The payment plan can never cover all trades, so these are summarized in a maximum of 15 payments.
The last installment (15th payment 3.5% of the total sum) is only due after all defects have been remedied.
It sounds logical, but I am inexperienced and somehow still suspicious. Thanks for the feedback.
we would work with a general contractor. We are buying the land directly from the owner and then building with the general contractor. He proposes the following payment plan based on the real estate agent and developer ordinance (the contract only comes into effect with the building permit or an existing development plan):
1. Payment installment before planning 9%
2. Payment installment after demolition/clearing 5%
3. Payment installment after setting up the construction site and completion of earthworks 11%
4. Payment installment after completion of the foundation slab 7%
5. Payment installment after completion of the basement ceiling 6%
6. Payment installment after completion of the ground floor ceiling 6%
7. Payment installment after completion of the upper floor ceiling 6%
8. Payment installment after completion of the shell construction 9%
9. Payment installment after completion of carpentry work 3%
10. Payment installment after completion of roofing work 3%
11. Payment installment after installation of the windows 8%
12. Payment installment after completion of rough installation 7%
13. Payment installment after completion of interior plastering 9.5%
14. Payment installment after completion of screed 7%
15. Payment installment after acceptance, rectification of residual defects, and readiness for occupancy 3.5%
What do you think?
We were concerned because after the screed not much is left open, but sanitary, doors, tiles, etc. are still missing.
The general contractor explained to us that we never have to make advance payments.
The costs for electrical work, heating work, sanitary installations, interior stairs, doors, access paths, and tiles are included in payments 12–14. The exterior plaster is included in the interior plaster work at point 13.
The payment plan can never cover all trades, so these are summarized in a maximum of 15 payments.
The last installment (15th payment 3.5% of the total sum) is only due after all defects have been remedied.
It sounds logical, but I am inexperienced and somehow still suspicious. Thanks for the feedback.