Before I start a new thread about the frost skirt, I’m going to ask for advice here directly.
Assuming a foundation cushion of 0.7m below ground level is sufficient (soil replacement) and the building is done with a frost skirt and without a basement. According to the soil report, the frost skirt should be 1m deep from the finished ground level. However, the underside of the slab equals the finished ground level.
1. If I execute the slab (20cm) finished top = finished ground level, is a frost skirt of 80cm sufficient? Overall, you then reach 1m including the slab.
2. Does the excavation contractor do the excavation for the frost skirt along with the excavation of the foundation cushion? Or do they only excavate a flat area of 0.7m x width x length and compact the gravel? And later, during the construction of the frost skirt, does the slab contractor excavate down to 1.1m? I find option 1 more complicated and have never consciously noticed it. The background is that, according to the construction specifications, the soil in the frost skirt area should be hand-excavatable for the slab contractor. But that does not make sense to me if they would have to excavate an additional 0.4m of soil.