lars909
2022-04-19 19:47:31
- #1
Hello everyone,
unfortunately, we discovered today at our new construction that the foundation was positioned incorrectly on the property. The slab has not yet been poured. Because an incorrect boundary stone was assumed, the foundation or the formwork is positioned 3 meters too far back on the property. We briefly considered accepting this and submitting a new building application but ultimately decided against it due to the lack of a garden.
The site manager immediately admitted the mistake. The foundation is now to be "shifted" 3 meters forward. If I understood correctly, a piece will be added at the front and connected to the rest. At the back, a new piece will also be added and connected – according to the site manager, the 3-meter protruding "rest" can remain since a terrace at the level of the sliding element is planned there anyway. The wastewater pipes, etc., will naturally also be shifted.
I am a layperson and, to be honest, still glad that the slab hasn’t been poured yet. Nevertheless, I am concerned whether this is the right approach? Or does everything actually need to be removed and redone? I don’t want to cause unnecessary effort and am satisfied with a reasonable solution. So what is structurally okay and justifiable? How is something like this handled in practice?
Best regards
unfortunately, we discovered today at our new construction that the foundation was positioned incorrectly on the property. The slab has not yet been poured. Because an incorrect boundary stone was assumed, the foundation or the formwork is positioned 3 meters too far back on the property. We briefly considered accepting this and submitting a new building application but ultimately decided against it due to the lack of a garden.
The site manager immediately admitted the mistake. The foundation is now to be "shifted" 3 meters forward. If I understood correctly, a piece will be added at the front and connected to the rest. At the back, a new piece will also be added and connected – according to the site manager, the 3-meter protruding "rest" can remain since a terrace at the level of the sliding element is planned there anyway. The wastewater pipes, etc., will naturally also be shifted.
I am a layperson and, to be honest, still glad that the slab hasn’t been poured yet. Nevertheless, I am concerned whether this is the right approach? Or does everything actually need to be removed and redone? I don’t want to cause unnecessary effort and am satisfied with a reasonable solution. So what is structurally okay and justifiable? How is something like this handled in practice?
Best regards