Foundation positioned incorrectly, what to do?

  • Erstellt am 2022-04-19 19:47:31

lars909

2022-04-19 19:47:31
  • #1
Hello everyone,

unfortunately, we discovered today at our new construction that the foundation was positioned incorrectly on the property. The slab has not yet been poured. Because an incorrect boundary stone was assumed, the foundation or the formwork is positioned 3 meters too far back on the property. We briefly considered accepting this and submitting a new building application but ultimately decided against it due to the lack of a garden.

The site manager immediately admitted the mistake. The foundation is now to be "shifted" 3 meters forward. If I understood correctly, a piece will be added at the front and connected to the rest. At the back, a new piece will also be added and connected – according to the site manager, the 3-meter protruding "rest" can remain since a terrace at the level of the sliding element is planned there anyway. The wastewater pipes, etc., will naturally also be shifted.

I am a layperson and, to be honest, still glad that the slab hasn’t been poured yet. Nevertheless, I am concerned whether this is the right approach? Or does everything actually need to be removed and redone? I don’t want to cause unnecessary effort and am satisfied with a reasonable solution. So what is structurally okay and justifiable? How is something like this handled in practice?

Best regards
 

11ant

2022-04-19 20:15:35
  • #2
You are not alone layman, your "site manager" obviously is too (or his brain is accidentally also three meters off). His problem is that his budget authority probably doesn’t allow for more; and his boss will be very satisfied with the "solution": a serious mistake indeed, but with obvious effects only well after the warranty expires. You should protest this botched job by all means! It is not only structurally nonsense to place the house on two slabs; but also energetically, because the misplaced slab section creates a first-class thermal bridge. I’ll call in ...
 

sergutsch

2022-04-19 20:18:24
  • #3
Actually, the correct procedure would be to have the staking done by the surveyor; the fact that the site manager is allowed to set it out personally is new to me. With us, the final staking plan was required as a subsidiary condition in the building permit.
 

sergutsch

2022-04-19 20:23:44
  • #4


look here :) (characters characters characters)

 

sergutsch

2022-04-19 20:25:26
  • #5
I would even strongly recommend catching up on it or at least checking and confirming it.
 

lars909

2022-04-19 20:28:38
  • #6
Wait. Before going into such a massive explanation here.

It is about the strip foundations under the formwork blocks. NOT about the slab. This has not been poured yet.
 

Similar topics
02.09.2013Angular bungalow on 800m² plot - financially feasible?16
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
14.07.2015Turnkey home. Free land17
26.05.2015Buy property or leave it?12
13.03.2018Turnkey Construction Land and Prices79
27.03.2017Backfilling for foundation slab25
04.03.2019No stopping zone in front of the property11
11.03.2019Is the base plate too deep (planned)?30
12.01.2020Raising the property by 2 meters - experiences?21
11.05.2021Neighbor is building a retaining wall on my property. What should I do?87
04.05.2020Assessment of land - hillside location15
09.09.2020The neighbor built foundations for a retaining wall on our property.10
11.01.2021Basement or slab? - Cost estimation24
19.10.2020Street about 50cm above the property - backfill or basement24
07.01.2021Recessed entrance in a prefabricated house: with or without a floor slab11
13.03.2021Basic line planning property slight slope29
12.07.2021Hang property, catch carport22
24.09.2022Neighbor grounding and drainage on our property41
30.08.2023Preparing the site for the floor slab on a slight slope15
14.09.2024Steel fence including foundation broken / tilted11

Oben