sauerpeter
2017-08-08 14:55:48
- #1
Hello,
our foundation slab is now finished and yesterday the construction of the ground floor began. The first invoice for earthworks and the foundation slab has already arrived. How does it generally work when I have paid? Do I thereby confirm that I accept the completed work and can no longer raise complaints about defects that may become apparent later? Or does this only apply upon the final acceptance of the entire building?
Our contract states the following:
Acceptance
1. The contractor is obliged to notify the client of the completion of the service verbally or in writing.
2. The client is obliged to accept the contractor’s service after completion within a period of 10 days at the latest, provided the service has been rendered without significant defects.
Hm...
our foundation slab is now finished and yesterday the construction of the ground floor began. The first invoice for earthworks and the foundation slab has already arrived. How does it generally work when I have paid? Do I thereby confirm that I accept the completed work and can no longer raise complaints about defects that may become apparent later? Or does this only apply upon the final acceptance of the entire building?
Our contract states the following:
Acceptance
1. The contractor is obliged to notify the client of the completion of the service verbally or in writing.
2. The client is obliged to accept the contractor’s service after completion within a period of 10 days at the latest, provided the service has been rendered without significant defects.
Hm...