Exchange of experience in rescheduling appointments

  • Erstellt am 2020-04-02 17:08:36

trksglm

2020-04-02 17:40:54
  • #1

Turnkey, yes. There is no construction schedule. And the payment plan is only defined to the extent that there are invoices in stages, so for example, when the foundation slab is completed, a payment becomes due, and so on.
 

ypg

2020-04-02 21:58:17
  • #2
You can't do anything at the moment. Breach of contract is out of the question. Whether you can get other craftsmen at all is also uncertain. Just plan for 3 or 6 months longer. We all do that, whether in house construction, school, visits to relatives, or vacations. Address the problem reasonably on the construction site. Don't be unreasonable.
 
Oben