You need at least 80cm of workspace + slope, so you have to calculate at least 1m in each direction on average. That results in 8 x 14.5 x 3 m³ with gravel and the base slab. In addition, there is a loosening factor, since you cannot pack the soil in the truck as densely as it was in the ground. Depending on the soil, you calculate with a factor of 1.1-1.2. So it will almost certainly be 400 m³ if the soil is not otherwise stored on the property ([den Mutterboden kann man ja eigentlich immer gebrauchen für die Gestaltung der Außenanlage]).