Waldfuchs888
2021-10-28 09:38:55
- #1
Hello everyone,
please provide an assessment of my cost breakdown. It is a shell home in timber frame construction.
The house + roof + roofing work will be delivered and erected.
Offers for the foundation slab, stairs, heating, screed are available, the rest are estimates.
Own contributions would be:
Building the installation level, insulating the installation level, finishing the attic, cladding walls with Fermacell, filling, flooring, partial tiling,
wallpapering and painting and the 1000 little things that have to be done...
The rest will be contracted out.
My concerns are as follows:
Additional costs:
Summary
please provide an assessment of my cost breakdown. It is a shell home in timber frame construction.
The house + roof + roofing work will be delivered and erected.
Offers for the foundation slab, stairs, heating, screed are available, the rest are estimates.
Own contributions would be:
Building the installation level, insulating the installation level, finishing the attic, cladding walls with Fermacell, filling, flooring, partial tiling,
wallpapering and painting and the 1000 little things that have to be done...
The rest will be contracted out.
My concerns are as follows:
[*]€400,000 for a single-family house with 155sqm seems very high to me, as it is a shell home and we are contributing a lot of own work.
[*]Have we forgotten any points?
[*]Have we seriously underestimated any points?
[*]Regarding own work: Is it even realistic to do all that yourself in a reasonable time? According to the advisor (seller), no problem, doable in four weeks of vacation...
Shell home | €232,800 |
Heating + sanitary rough-in | €42,000.00 |
Stairs | €6,650.00 |
Electricity | €25,000.00 |
Flooring | €7,500.00 |
Filler compound | €2,000.00 |
Doors | €5,000.00 |
Screed | €8,500.00 |
Sanitary fixtures | €6,000.00 |
Foundation slab | €25,000.00 |
Additional insulation | €5,000.00 |
Plaster, wallpaper, paint | €5,000.00 |
More gypsum boards | €2,000.00 |
Earthworks (probably too low, as approx. 100t of concrete from demolition must be disposed of) | €13,000.00 |
Tiler | €2,500.00 |
Additional crane costs | €8,000.00 |
Energy consultant KfW | €2,000.00 |
Bathroom installation | €2,500.00 |
Total | €400,450 |
Additional costs:
Surveying | €2,500.00 |
Builder's liability insurance | €600.00 |
Construction performance insurance | €1,500.00 |
Builder helper insurance | €750.00 |
Soil report | €800.00 |
Water connection | €1,200.00 |
Sewer connection | €2,000.00 |
Electricity connection | €2,500.00 |
Construction power | €1,000.00 |
Construction water | €400.00 |
Waste disposal | €500.00 |
Construction site toilet | €500.00 |
Notary, tax, mortgage | €5,000.00 |
Development of 50m (we want to do ourselves) | €8,000 |
Total | €26,250.00 |
Summary
House | €400,450.00 |
Additional costs | €27,250.00 |
Photovoltaic system | €15,000.00 |
Kitchen | €15,000.00 |
Buffer | €40,000.00 |
Architect / construction supervision | €12,000.00 |
Total costs overall | €504,200.00 |