Contractual penalty in the general contractor work contract

  • Erstellt am 2024-01-30 17:06:38

Schnubbihh

2024-01-30 17:06:38
  • #1
Hello dear community,

I just had a conversation with my GU about the contract for work and received a verbal confirmation that a penalty clause for delay can be included in the contract for work. Now I am wondering how this could be best formulated. Of course, I know that I could/should ask a specialist lawyer for this now. But I am interested in whether you have any experience on this topic and/or possibly have a clause in your contract that you could share here?

Currently, I am thinking of the following:
The move-in date for the completed house is 01.12.2024.
In the event that the move-in date is not met, a penalty of €500 per started calendar week will be due, but in total no more than 5% of the agreed contract price. The penalty is independent of any fault on the part of the contractor and can be claimed up to the handover of the house and is due and payable with the final payment.
 

hanghaus2023

2024-02-02 09:23:27
  • #2
Your wording will certainly not be accepted by the contractor. It must always be included that the contractual penalty is only due if the contractor is responsible for the delays. You can surely find something on the internet about that.
 

hanghaus2023

2024-02-02 09:28:22
  • #3
I found that within 10 seconds.

Found after 10 seconds

Penalty for completion
The contractor commits to paying a penalty of _____ % of the agreed net contract sum per working day of delay in case of exceeding the agreed _____ (completion date) for which he is responsible, but a maximum of 5 % of the net contract sum in total. The assertion of damages beyond this is not excluded. The client can claim the penalty up to the final payment.
If the completion date is postponed due to circumstances for which the contractor is responsible, the penalty will be forfeited in the event of delay by the contractor regarding this new _____ (completion date).
 

jens.knoedel

2024-02-02 09:28:42
  • #4

The fault must be changed. For example, if Russia attacks Poland, deep winter starts as early as November, or floods occur in summer, you will not be able to blame the general contractor. Such points are always removed.
 

Nida35a

2024-02-02 09:44:29
  • #5
Saving on a lawyer for possibly the most expensive investment in life is naive and grossly negligent in the current situation. If the general contractor is open, I would always have the contract reviewed, my points would be insolvency protection, completion guarantee, deadlines, payments, withholdings, etc. Our two-hour appointment led to changes we had no idea about. If you have a company with glossy brochures, a huge legal department, etc., they rather do not change anything in their contract documentation.
 

Similar topics
28.04.2014Cost estimate - contract for work16
07.05.2015Have the work contract checked by a professional37
06.07.2015Termination of work contract for house construction (before construction)14
06.12.2016Contract for work before property purchase - real estate acquisition tax?10
22.02.2016Signature of the work contract before financing?15
04.07.2016Purchase of property under a work contract12
19.07.2016When did you sign the work contract? Prior planning?12
08.08.2018Withdrawal from the work contract within the withdrawal period23
02.11.2018Contractual penalty for sale/rental within x years12
26.09.2019ScanHaus Work Contract Additional Agreement14
24.11.2019Exceeding the construction time, contractual penalty22
27.01.2020How do I get out of a contract for work?11
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
07.05.2022Work contract with exclusion §14/1522
01.07.2023Provision interest and deadlines of the house building company in the work contract13
25.12.2023Behavior in case of imminent delay by the property developer48
06.08.2023Work contract individual or lump sum?11
06.09.2024Contractual penalty in the Building Code contract - new construction20

Oben