Good morning forum,
has anyone here had experience with how much you really save if you take on the house construction yourself and contract the trades individually?

The following scenario:
We had actually found a suitable partner, a very well-known provider in Germany who builds with aerated concrete blocks. Here, building a city villa of about 9 x 10 meters would cost around €300,000 (without basement and without tiles/laminate).

Now, an acquaintance said, get an architect and inquire the trades individually.

Assuming I now take a plan and contract the trades individually (civil engineering, roof structure, electrical, windows, heating, screed - to name the main points), how much do you really “save”?
Thanks for your answers.
 

Tassimat

2020-05-18 09:42:41
  • #2
Search for an architect and ask him at what cost he can build the desired house. Do not forget the architect's fee.
 

XAMMAX2

2020-05-18 09:46:14
  • #3
But the architect doesn’t organize the trades, right?
 

Tarnari

2020-05-18 11:07:39
  • #4
Sure, he can do that. The only question is what the architect is commissioned with. Ours basically does everything. Tendering, comparisons, awarding (of course we sign), site management, acceptance, etc.
 

Alkaral

2020-05-18 11:16:42
  • #5
We faced the same choice, and I am glad about it. Most people don’t even have the option. If you were lucky enough to have simply bought a plot of land and can now more or less do whatever you want, you should definitely go with the architect (we did that too):

1. You are the one who pays the craftsmen, and they listen to you!
2. You should bring in an independent building expert, e.g. from the Verband Privater Bauherren, who will also check the contracts, e.g. the architect contract.
3. First of all, I would start planning myself with paper and pencil (or a construction planning program). Then start a small architect tender to see who can build this roughly sketched house for you and talk to about 4-5 architects.
4. Try to inform yourself about everything, e.g. here in the forum.
5. Then you will have significantly less trouble than if you go with a general contractor..

Good luck
 

Grantlhaua

2020-05-18 11:38:38
  • #6
I don’t think I had a single contract for our house. The most formal thing was a signed offer, the rest was done by handshake. However, if you get an architect who accompanies everything up to the handover of the keys, you probably won’t save a single cent compared to the general contractor.
 

Similar topics
23.10.2008We need an architect - or should I do it myself?14
02.01.2009Experiences with architects15
19.03.2013Turnkey or build with architects?19
21.07.2013Cost estimates from two architects differ greatly!10
13.11.2013Do you absolutely need an architect?10
16.12.2013Pre-planning with the architect - is having your own floor plan sensible?18
30.01.2014Architect's cost estimation15
21.08.2014Construction costs when building with architects. What does your experience say?18
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
19.12.2014Finding architects - but how?26
08.09.2015Massive house by the architect, approximate costs?16
23.09.2015Responsibilities of the Architect in Tendering18
29.10.2015Is it normal for the purchase of land to be tied to an architect?16
19.01.2016Construction project with architects31
20.08.2016Should the house be planned by a general contractor or architects?30
10.03.2017Payment of the architect16
12.10.2017Cost of enclosed space. First draft discussed with architects27
27.10.2017Construction description by architects: Who has experience?13
07.02.2018Architect's suggestions disappointing - What next?32
12.02.2024Preliminary design via the architect and then tendering?16

Oben