Construction water costs for shell construction

  • Erstellt am 2011-03-09 17:54:24

annerubia

2011-03-09 17:54:24
  • #1
Hello everyone,

we have now already been told by phone about a construction water bill of €300(!) during the shell construction phase of our solid single-family house without a basement. So far, we have only completed the ground floor.
It seems a bit excessive to us.
Okay, a hydrant had to be tapped. But can it really be that much for us already???
Or are we then paying the costs of our neighbors who are almost finished???
The builder spoke of the bill since November (as already said, for us the strip foundation, base slab, and pore concrete blocks - ground floor are completed).

Isn't our builder obliged to provide us with the water bill showing our exact consumption?

We have now requested this bill first (let’s see how many cm³ it actually is and how many other charges there are).

But we would like to get an assessment from experts first.

Many thanks in advance!

Annerubia
 

annerubia

2011-03-10 19:05:52
  • #2
So it's supposedly 7m³. Given what has been done so far, that's a bit much, isn't it??? The rest of the 280€ are fees.
 

Thommi

2011-03-10 20:57:43
  • #3
Smells like a rip-off to me. 7000 liters of water to glue one floor and wash out some tools ??????????
 

annerubia

2011-03-10 21:42:25
  • #4
In the end, it's not about the few consumption euros. But about the principle. The water just wasn't enough for our foundation and the few stones. And since the construction of the neighbor's house used the same hydrant, I think we should at least share the costs, right??? I will inquire again with the [Wasserwerk] about the high basic costs.
 

annerubia

2011-03-13 18:06:04
  • #5
I suppose so. But it is a strip foundation and the footing. The contractor cannot charge construction water at the neighbor's, as the clause was removed from their contract. Of course, he is trying to get it back from us. It will probably be the same with the construction electricity, which we have not used much so far. But not with us...!!!
 

Similar topics
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
03.01.2016surprising bill, no cost estimate12
27.08.2016Different window heights on the ground floor and upper floor14
18.11.2016Electrician's invoice after 2.5 years - What are my rights?18
21.02.2017Development plan difference between ground floor, roof, and single-storey17
17.10.2011Need an invoice for an IKEA BESTÅ BURS TV bench21
28.03.2017Invoice land registry entry not for all buyers?13
18.08.2017First invoice for earthworks and base slab due25
19.10.2017Invoice from the notary - 4 days after the notarization appointment11
08.03.2018Invoice for water connection despite payment through property price?35
10.08.2018Landscaping company - defects, high bill, no warranty?!13
03.07.2025BG Bau is sending us a high bill - can I defend myself against it?14
11.03.2020Architects invoice - Amount okay?13
12.11.2020Craftsman invoice for replacement of defective tool27
02.02.2021The contractor wants to issue an invoice for planning services60
10.12.2021General contractor's offer vs. final invoice - a nightmare19
15.01.2022Floor plan planning semi-detached house, ground floor assessment20
28.05.2025Floor plan: who has the master bedroom on the ground floor?54
02.10.2024Underfloor heating on the ground floor: insulate or not?16

Oben