Construction of a turnkey single-family house

  • Erstellt am 2015-06-23 15:48:12

Lassemann

2015-06-24 23:12:46
  • #1
June 2014: Land purchase
until September: Selection of architect
until November: Design and approval planning (building application 5.11.)
until mid-January: Waiting for building permit / Preliminary selection of samples
until mid-February: Demolition of old building
until end of February: Clearing and felling of trees (28) / Soil investigation / Confirmation of unexploded ordnance clearance
Beginning of March: External development of the property
March 11: Groundbreaking.....
June 12: Topping-out ceremony
Currently: Window installation and roof covering

Goal: Move in by the end of September..... (buffer until end of October)
 

ypg

2015-06-24 23:21:42
  • #2
: Question read?
 

Lassemann

2015-06-24 23:23:21
  • #3
Yes, sure. How much longer will it take. There were answers. An example is our current one.

Annoyed?
 

Bauexperte

2015-06-24 23:27:54
  • #4

Treading on your toes ...?

Rhineland greetings
 

ypg

2015-06-24 23:52:42
  • #5


You are probably only annoying the OP, who is waiting for the start of their construction. Therefore, your post does not add any value to the original question.
 