Conditions for independent building experts

  • Erstellt am 2016-07-19 23:20:45

chaqrou

2016-07-19 23:20:45
  • #1
Hello everyone,

I have been a silent reader for a long time. Now things are becoming more concrete for us, the plot is reserved, the general contractor is probably found, and construction supervision possibly too. In addition to the construction supervision, the construction documents, contract for work, and soil report from the municipality are to be checked by the independent expert (Dipl. Eng. Architect FH). After reviewing the documents, I will negotiate them with the general contractor and hope that the contractor will accept as many as possible.

I have a few questions regarding the conditions and contents of his offer.

I have already searched for prices in the forum, but only found the two big providers with 3 and 4 letters. These are around €80-100 including VAT. My construction expert charges:

€107 net per hour
-5% discount (a buddy shares the office with him)
+8% overhead costs
+19% VAT
= €130.64 gross per hour

He has scheduled 5 on-site appointments of one hour each; additional time spent will, of course, also be charged.

Travel time to and from the site, about 30 minutes each way, will also be charged at the billing rate plus mileage allowance.

No documentation after the appointments is planned. If defects are found, he will clarify them directly with the site manager.

Telephone calls with me, the general contractor, or emails will also be invoiced based on time spent.

I expect total costs of just under €3,000 gross for 6-7 appointments with 1.5 hours on-site, examination of the construction documents, the contract for work, and the property documents.

Of course, I understand if he charges for his invested time. It just sounds to me as if he will bill every little detail meticulously, even though he says he won’t bill so meticulously.

I look forward to your opinions and suggestions for improvement.

If this is allowed, I would like to attach an excerpt of the offer without mentioning the [Bausparvertrag].
 

Bauexperte

2016-07-19 23:22:40
  • #2


Rhineland greetings
 

Bauexperte

2016-07-19 23:24:45
  • #3
Good evening,


Yes, that is of course possible; just please remove any proof of origin and names.

Rhenish greetings
 

chaqrou

2016-07-19 23:28:55
  • #4
 

Bieber0815

2016-07-20 12:37:11
  • #5
The prices offered are okay from my point of view. The only thing I find somewhat exaggerated is the regular hourly rate for driving plus the kilometer flat rate; it also includes overhead costs. However, it's probably not worth negotiating at this point (how many kilometers are there?).

With a total of 3000 euros, you have also chosen a reasonable budget in my opinion, so additional site visits are possible.

Creating the documentation only when it is really necessary is very sensible! I like that, if he doesn't notice anything, he doesn't have to do anything further and it doesn't cost any additional money. And he reports problems best directly to your contractual partner anyway.

Also: I see the meticulous billing as rather positive, also for you.
 

chaqrou

2016-07-20 14:00:48
  • #6
Per site visit, it is 50 km. Thus, the on-site costs (1.5h) at the construction site are just under €200 gross. As I read it, the €0.68/km plus the 8% overhead costs and VAT are added. So for the total 1 hour of travel time, approximately €170 gross. Total costs per site visit would therefore be €370 for 1 hour of travel and 1.5 hours on-site. I just discovered the Kfw program 431. Unfortunately, my building expert is not listed there. Now I am considering getting a second offer from one based in the construction location.
 

Similar topics
28.04.2014Cost estimate - contract for work16
13.09.2016Looking for construction supervision NRW, Münsterland16
17.02.2015KFW funding sensible / Energy advisor, construction supervision?10
07.05.2015Have the work contract checked by a professional37
06.07.2015Termination of work contract for house construction (before construction)14
11.09.2016KfW - Construction supervision / verification / acceptance23
06.12.2016Contract for work before property purchase - real estate acquisition tax?10
03.01.2022Construction supervision via Bauherren-Schutzbund, Association of Private Builders, TÜV, DEKRA, independent expert surveyor, or "xyz"...?57
22.02.2016Signature of the work contract before financing?15
09.07.2016Construction supervision in the Dortmund area: Association of Private Builders or SV11
04.07.2016Purchase of property under a work contract12
19.07.2016When did you sign the work contract? Prior planning?12
18.08.2017First invoice for earthworks and base slab due25
19.11.2017Contract law, law, construction expert12
08.08.2018Withdrawal from the work contract within the withdrawal period23
26.09.2019ScanHaus Work Contract Additional Agreement14
27.01.2020How do I get out of a contract for work?11
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
07.05.2022Work contract with exclusion §14/1522
01.07.2023Provision interest and deadlines of the house building company in the work contract13