bauenmk2020
2019-09-15 14:07:10
- #1
Hello everyone,
we are building with a general contractor (GU). The construction service description includes the earthworks / civil engineering / foundation. However, after consulting with the site manager, we have removed this part and are carrying it out ourselves. A friend of my wife who is a civil engineer is available to us for this. Our plot only has a slight slope. We are building without a basement. So the work is manageable.
We have now received a credit of about 5,000 EUR. Omission of frost skirts including excavation, earthworks, topsoil removal, production of gravel cushion.
Instead of the frost skirts with clean layer, a gravel cushion with sub-base insulation for the foundation slab will now be used. This insulation was quoted at about 4,200 EUR. On average, we therefore only save about 800 EUR on earthworks!
The site manager said that it is still better this way, as the additional costs according to the construction service description are not yet included in the 5,000 EUR. And with the friend's civil engineer, we could immediately prepare the terrace, double garage, drainage, crane standing area, etc.
Unfortunately, we will never know in this way what we ultimately "saved" or overpaid. But what do you think: Is it okay to do it this way? According to the site manager, we would save at least the 20% markup from the general contractor. Is it wise to do without the frost skirts and instead equip the foundation slab with the sub-base insulation?
we are building with a general contractor (GU). The construction service description includes the earthworks / civil engineering / foundation. However, after consulting with the site manager, we have removed this part and are carrying it out ourselves. A friend of my wife who is a civil engineer is available to us for this. Our plot only has a slight slope. We are building without a basement. So the work is manageable.
We have now received a credit of about 5,000 EUR. Omission of frost skirts including excavation, earthworks, topsoil removal, production of gravel cushion.
Instead of the frost skirts with clean layer, a gravel cushion with sub-base insulation for the foundation slab will now be used. This insulation was quoted at about 4,200 EUR. On average, we therefore only save about 800 EUR on earthworks!
The site manager said that it is still better this way, as the additional costs according to the construction service description are not yet included in the 5,000 EUR. And with the friend's civil engineer, we could immediately prepare the terrace, double garage, drainage, crane standing area, etc.
Unfortunately, we will never know in this way what we ultimately "saved" or overpaid. But what do you think: Is it okay to do it this way? According to the site manager, we would save at least the 20% markup from the general contractor. Is it wise to do without the frost skirts and instead equip the foundation slab with the sub-base insulation?