Change or choose your temporary power supplier yourself

  • Erstellt am 2017-05-16 15:42:22

Hoeffa

2017-05-16 15:42:22
  • #1
Hello community,

we have now had construction power for a month and are being supplied through the "basic supply" from E.On. E.On is known to not be the cheapest. Has anyone here ever changed the supplier during the time of construction power? I am allowed to cancel every 14 days and during the first cautious search I found some providers that are 5 cents/kWh cheaper and also cancellable every 2 weeks (which is what matters).

I am also a bit shocked by the unexpectedly high electricity consumption in the first 4 weeks. It was 581 kWh. The ground floor including ceiling is in the shell construction stage, there is no crane on site (ceiling via mobile crane). So basically only stones were cut and concrete mixed. However, there is a construction trailer of the general contractor on site which was heated during the first days in April, as it was still quite cold then. You don't really want to forbid that, although I would have preferred if they had warmed themselves up by working :-P

In any case, one is now naturally thinking about how much electricity will be wasted in the next 5 months, especially once things really get going.

Thanks for tips and info!
 

Hoeffa

2017-05-16 17:19:52
  • #2
+++ is no longer relevant. The client probably gave the wrong meter reading out of shock and 581 kwh became 81 kwh. +++
 

meister keks

2017-05-16 22:50:57
  • #3
Even if it were that high. With the things that need to be done at the moment and the things that had to be done before, it doesn't matter at all. That little bit of electricity consumed there would be totally irrelevant to me.
 

ypg

2017-05-17 01:11:48
  • #4
I believe anyway that you have to take the basic supplier MUSS.

Electricity and water should – like other "small things" – be generously calculated – the more you look forward to the savings (which anyway are swallowed up again by the bigger items )
 

Steffen80

2017-05-17 07:36:32
  • #5
Insanity... this is about maybe 100..150 EUR savings. Hope you have thought the house construction through well. Anyone who has to calculate like this... maybe better not build a house at all..
 

ONeill

2017-05-17 10:58:29
  • #6
I am not worried about my house construction, but I would take 150 euros if I could save them. [emoji4]

I had tried a switch back then with the registered meter number, but was rejected. So I would definitely agree with my predecessors that construction power only goes through the basic supplier.
 

Similar topics
06.12.2017Until when must construction power be taken?22
23.06.2015Secondary construction costs, amount of construction electricity/construction water, how much?18
07.01.2016Basic utility provider house connection - then switch provider?11
29.04.2016Organize construction electricity/construction water yourself?31
31.10.2016Heating the screed with the utility provider?!12
19.10.2017Temporary power supply - What costs are involved?19
05.07.2018Temporary electricity stolen - amount of compensation?17
20.07.2018Construction power or house connection? How much construction power is needed?12
19.03.2019Construction power is being connected. Does the builder have to be present?10
20.05.2019Temporary power also through alternative suppliers?10
04.10.2019Easily switch temporary power provider?21
11.05.2020Construction power help, who can give tips?17
10.01.2022Determine construction power costs / eOn charges too much36
23.10.2023Judgment on construction power supply - assessments / experiences?10
09.10.2024Construction electricity/construction water costs are the responsibility of the builder11

Oben