We are having a dispute with a company that installed the sand base.
It was about a work area of 14 x 15.5 m (217 sqm).
The installed sand base had an average thickness of about 30-35 cm, and the same thickness of topsoil was removed.
The question now is,
- how much topsoil must be transported away
- how much fill sand must be brought in and installed?
- what volume changes must be expected for topsoil and fill sand?
Thank you in advance for any suggestions.
Regards
Stefan
PS: Hope this belongs here
We are having a dispute with a company that installed the sand base.
It was about a work area of 14 x 15.5 m (217 sqm).
The installed sand base had an average thickness of about 30-35 cm, and the same thickness of topsoil was removed.
The question now is,
- how much topsoil must be transported away
- how much fill sand must be brought in and installed?
- what volume changes must be expected for topsoil and fill sand?
Thank you in advance for any suggestions.
Regards
Stefan
PS: Hope this belongs here