Builder - cost-neutral changes that now do cost money

  • Erstellt am 2012-07-19 14:03:34

siebert

2012-07-19 14:03:34
  • #1
Hello,

we are building with a developer (contract not yet signed). We have had the plans for the ground floor changed (open kitchen instead of a separate room). Since this is a load-bearing wall, a steel beam must be installed. We have already received a printout from the developer stating "Änderung Küche EG - kostenneutral möglich". Now, shortly before signing the contract, we have suddenly been charged 600 euros for the kitchen change. When I asked why it was initially stated as cost-neutral, the answer was: yes, we would have liked to do it, but unfortunately, it is not possible after all.

Is this really normal business practice? I guess we have no choice but to swallow it and pay another 600 euros.

Building really is only associated with trouble!!!
 

Der Da

2012-07-19 15:15:10
  • #2
I wish you good nerves.... this is just the beginning. Wait until the authorities come into play .... hehe

I would ask myself, do we have other such points. What would it cost if each point is then charged separately. The 600 € is peanuts, but if it’s always like this, you start to wonder where it will end. I would have a very clear word with the developer, and above all, put in writing what you agree on afterwards... not just notes in the margin, but contract additions.
 

Cascada

2012-07-19 16:34:41
  • #3
Hello,

as far as I know, changes are charged accordingly.
Example: a window is removed - cost reduction. Moving walls - neutral, as long as no changes to the structural engineering are necessary.
Maybe your developer meant it that way and it was not immediately foreseeable that structural concerns were involved. Now they are, and additional costs arise.
Perhaps the whole matter was just phrased somewhat awkwardly.

By the way, the Da is right - even with supposedly good planning, some additional costs will still arise. Therefore, plan a certain reserve for incidental construction costs.

Regards...
 

Bauexperte

2012-07-19 17:43:19
  • #4
Hello,

I assume – since you are obviously about to sign the contract – and the plans were probably largely finalized, that you do not have to pay anything for the redrawing?

You don’t have to “swallow” anything – you simply deviated from the originally calculated variant. By removing the load-bearing wall, additional costs arose due to the necessary beam, which you have to bear.

Your provider could also have waited until the statics were submitted and then presented you the invoice. His procedure is fair in this way, as you can still switch back to the original planning cost-neutrally. After submission of the statics, this is no longer so easily possible; then you would have had to bear additional costs for recalculation.

Not necessarily; with a little calm and reflection, on the contrary.

Best regards
 

perlenmann

2012-07-20 07:45:24
  • #5
Possibility ("something is possible") colloquially denotes a rather vague low probability of an event occurring, which is to be regarded as a personal opinion.

Thanks Wiki

The rest has already been said by Bauexperte.
And annoyance or stress and extra charges will still come a whole lot!
 

Häuslebauer40

2012-07-20 10:29:19
  • #6
When I read all this, it seems that we made a good choice with our general contractor regarding changes. All changes were free of charge up until the signing of the final work plans, within a certain scope, of course, even though completely new preliminary plans were created after each change. Naturally, additional services related to the construction project, such as extra windows, etc., were included in an adjusted house price, but shifting/extending/shortening walls, even if it slightly altered the structural engineering, remained free of charge. Only when signing the final work plans were we made aware that from then on any changes would be subject to charges because the wall elements would then go into production.
 

Similar topics
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
03.08.2012Contract Supplement to the Construction Contract by the Developer36
24.07.2013Additional costs due to underfloor heating11
23.06.2014Developer charges heavily for replanning - justified?12
01.03.2015The developer does not build according to the plan14
13.06.2015New construction with developer / construction drawing documents23
24.04.2017Lighting in hallway and kitchen: Are recessed ceiling spotlights needed?19
24.12.2015Single-family house, Energy Saving Ordinance 2016, developer recommends additional insulation - is it sensible?39
28.05.2019Building without work plans133
14.11.2016Soundproofing - weakest link? (Windows?)26
03.12.2019Additional costs due to incorrectly planned ventilation system + floor-to-ceiling windows?50
22.05.2017Almost every window has scratches - what is considered normal?22
29.01.2018Windows on the roof terrace are installed "strangely".21
01.08.2018Description of construction services - Performance assessment?12
06.08.2019First conversation with the developer - first numbers...64
22.02.2022Checklist Electrical Planning New Construction Developer10
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
22.12.2024Floor plan changes for end-terrace house from the developer133
12.09.2023Tile installation with additional costs for large format11
14.05.2024Window drive for tilt-and-turn windows or manual?11

Oben