Steve55
2024-07-24 07:48:37
- #1
Hello everyone,
I am a bit desperate and have been racking my brain lately regarding the earthworks for a foundation slab.
Unfortunately, I was too trusting and believed an earthworks contractor who said that 1.7m of excavation was necessary (according to the soil report). But this turned out to be incorrect!!! He even dug deeper because he thought the clay soil was not load-bearing. Now groundwater has been encountered.
This too deep section (1/3) of the excavation pit was then filled back with soil!!! which, of course, came out again because luckily it was noticed. Afterwards, rubble was placed and on the remaining part (2/3) of the still moist pit, mineral concrete 0/32 was applied and compacted. Now a geotextile was laid, then ring earth electrode and another layer of mineral concrete/gravel 0/32. That is the current status. On average, now another 1.5m-2m of gravel must be applied.
Thus, the excavation pit had an estimated slope of 10 degrees at the base… but it is now almost leveled.
I have since terminated the cooperation with the earthworks contractor due to lack of expertise. However, this has cost me quite a bit of money because the down payment is lost.
Now my questions:
1. Is the slope at the base a problem? Or should it have been completely level?
2. Could the groundwater encountered underneath the rubble cause problems regarding settlements? (Clay/silt)
3. The subgrade was not evenly scraped off and was moist… Problem regarding compaction of the 0/32 gravel and settlements?
4. The excavation pit will remain open for 1-2 months. Problem regarding rain?
5. Can it be left as is because a huge gravel layer will come on top anyway or what can I do? Bring in a geotechnical engineer who also did the report?
I am already at my wit’s end and have just started.
Thank you very much in advance.
Best regards Steven
I am a bit desperate and have been racking my brain lately regarding the earthworks for a foundation slab.
Unfortunately, I was too trusting and believed an earthworks contractor who said that 1.7m of excavation was necessary (according to the soil report). But this turned out to be incorrect!!! He even dug deeper because he thought the clay soil was not load-bearing. Now groundwater has been encountered.
This too deep section (1/3) of the excavation pit was then filled back with soil!!! which, of course, came out again because luckily it was noticed. Afterwards, rubble was placed and on the remaining part (2/3) of the still moist pit, mineral concrete 0/32 was applied and compacted. Now a geotextile was laid, then ring earth electrode and another layer of mineral concrete/gravel 0/32. That is the current status. On average, now another 1.5m-2m of gravel must be applied.
Thus, the excavation pit had an estimated slope of 10 degrees at the base… but it is now almost leveled.
I have since terminated the cooperation with the earthworks contractor due to lack of expertise. However, this has cost me quite a bit of money because the down payment is lost.
Now my questions:
1. Is the slope at the base a problem? Or should it have been completely level?
2. Could the groundwater encountered underneath the rubble cause problems regarding settlements? (Clay/silt)
3. The subgrade was not evenly scraped off and was moist… Problem regarding compaction of the 0/32 gravel and settlements?
4. The excavation pit will remain open for 1-2 months. Problem regarding rain?
5. Can it be left as is because a huge gravel layer will come on top anyway or what can I do? Bring in a geotechnical engineer who also did the report?
I am already at my wit’s end and have just started.
Thank you very much in advance.
Best regards Steven