Cicero
2011-06-12 13:51:52
- #1
Hello,
we are not really making progress, maybe someone can help me ..
- New building is in place.
- The plot is not yet completely filled (about 35-50 cm missing).
- Basement plinth: reinforcement plaster, fabric embedding, smoothing,
over-troweling has been done.
- Waterproof basement with perimeter insulation.
How to proceed now:
We would like to lay border stones, make a terrace, backfill:
Does the reinforcement plaster that will later be below ground level still need to be protected by a dimpled membrane or thick slurry?
What is the correct order?
Thick slurry - dimpled membrane - laying and compacting gravel for terrace? (won't the dimpled membrane tear again) - laying border stones (also around the later terrace) - finishing wooden terrace - backfilling?
Thanks in advance
we are not really making progress, maybe someone can help me ..
- New building is in place.
- The plot is not yet completely filled (about 35-50 cm missing).
- Basement plinth: reinforcement plaster, fabric embedding, smoothing,
over-troweling has been done.
- Waterproof basement with perimeter insulation.
How to proceed now:
We would like to lay border stones, make a terrace, backfill:
Does the reinforcement plaster that will later be below ground level still need to be protected by a dimpled membrane or thick slurry?
What is the correct order?
Thick slurry - dimpled membrane - laying and compacting gravel for terrace? (won't the dimpled membrane tear again) - laying border stones (also around the later terrace) - finishing wooden terrace - backfilling?
Thanks in advance