Canca42
2016-05-18 21:47:06
- #1
Hello to all previous builders,
we want to build a single-family house 150 sqm (footprint approx. 91 sqm), 1 1/2 stories with 180 Drempel on a slab-on-grade foundation.
We have received some offers from [BU] (prefabricated wooden houses) ... we have decided that the house should have [KFW 55] standard. Now the question of the slab-on-grade construction, a building description looks for example like this
- Topsoil removed & stored on the side max 30 cm, foundations are excavated
- Installation of max. 30 cm fill under the slab with compaction, 2.5 m fill all around
- Exterior foundation concrete C 20/25 - steel reinforcements 2 pcs. 8 mm rebar
- Slab made of reinforced concrete C20/25, thickness 20 cm, reinforcement steel mesh 2 x O188 A, protective foil laid below the slab
- Foundation earth conductor installed
- Sewer pipes for wastewater below the slab up to the outer edge of the foundation
- Plinth - wall plaster ends at the top edge of the slab, front side of the slab is provided with polystyrene rigid foam board
That was it at a relatively reasonable price. However, and we know this, a few points are still missing like empty conduits, house connections, etc. according to the [BU] all possible at a low extra cost. I do not trust it, however ... another [BU] building [Kfw 40] says that the slab should be at least 25 - 30 cm thick, foundations made of steel fiber concrete, gravel layer under the slab, insulation Styrodur under the slab.
Who can tell me something about this or share their experiences? What additional costs come with the slab, e.g. graveling of the driveway for the crane - what extra costs can be expected?
Many thanks in advance for your assessments.
we want to build a single-family house 150 sqm (footprint approx. 91 sqm), 1 1/2 stories with 180 Drempel on a slab-on-grade foundation.
We have received some offers from [BU] (prefabricated wooden houses) ... we have decided that the house should have [KFW 55] standard. Now the question of the slab-on-grade construction, a building description looks for example like this
- Topsoil removed & stored on the side max 30 cm, foundations are excavated
- Installation of max. 30 cm fill under the slab with compaction, 2.5 m fill all around
- Exterior foundation concrete C 20/25 - steel reinforcements 2 pcs. 8 mm rebar
- Slab made of reinforced concrete C20/25, thickness 20 cm, reinforcement steel mesh 2 x O188 A, protective foil laid below the slab
- Foundation earth conductor installed
- Sewer pipes for wastewater below the slab up to the outer edge of the foundation
- Plinth - wall plaster ends at the top edge of the slab, front side of the slab is provided with polystyrene rigid foam board
That was it at a relatively reasonable price. However, and we know this, a few points are still missing like empty conduits, house connections, etc. according to the [BU] all possible at a low extra cost. I do not trust it, however ... another [BU] building [Kfw 40] says that the slab should be at least 25 - 30 cm thick, foundations made of steel fiber concrete, gravel layer under the slab, insulation Styrodur under the slab.
Who can tell me something about this or share their experiences? What additional costs come with the slab, e.g. graveling of the driveway for the crane - what extra costs can be expected?
Many thanks in advance for your assessments.