Are partial construction phase approvals common with general contractors?

  • Erstellt am 2019-03-26 21:54:28

Lucrezia

2019-03-26 21:54:28
  • #1
Hello everyone!
After months of searching, we decided on a local carpentry company that is a bit more expensive but has an excellent reputation in the area.
We are now encountering the first inconsistencies: the contract is actually a scope of work with a few rough payment targets.

At our request to define inspections for the construction phases, we were told that the inspection only takes place at the end; there are no inspections in between.
The explanation for this: the carpentry company, in our case [GU], is responsible for all trades, so only a final inspection would make sense.

Are there other clients here who only had a final inspection?

Is it even okay if no intermediate inspection is conducted with [GU]?
 

Nordlys

2019-03-26 21:57:01
  • #2
That's right. Completely normal. If you pay for one step, you have accepted it. Then comes the final acceptance and the remaining payer, done.
 

Lucrezia

2019-03-26 22:02:38
  • #3
... And the acceptances must be defined in the contract, right?
 

Nordlys

2019-03-26 22:06:45
  • #4
No. You have a small local craftsman as a partner. He does not indulge in iura and paperwork, he builds. You pay and thus create a fact. He says what I got is okay, so money is paid. Be glad that you get a contract at all. We had none, only a handshake, a construction service description, very rough, a payment plan, very rough, and a promise to be allowed to deduct a discount if payment is made within eight days. That works too.
 

Lucrezia

2019-03-26 22:24:52
  • #5
Where did you build, Karsten? I thought everything done by handshake and good reputation in the village was only possible in the deepest Bavaria :D
 

schubert79

2019-03-26 22:25:51
  • #6
Acceptance at the very end!
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben